- Build a realistic work plan: task breakdown, dependencies, critical path and float.
- Link the budget to activities through unit costs, and calculate cost per person and cost per result.
- Monitor implementation with the burn rate and detect underspending and overspending early.
Keep the course at home: free PDF handout with exercises, key takeaways and quiz answers.
1From logframe to work plan
The logframe says what; the work plan says who does what, when and with what resources. Start from the logframe activities and break them down into tasks of 1 to 4 weeks (work breakdown structure): to "distribute transfers to 3,000 households", you must register, verify, contract a payment provider, train the teams, inform communities, pay, and carry out post-distribution monitoring.
Each task receives a duration, a single person responsible and its dependencies: most are "finish-to-start" (payment can only start after the contract is signed). The Gantt chart shows these tasks over time, but it is not enough: the critical path must be identified.
The work plan also integrates context constraints: rainy season cutting off roads, lean season, religious holidays, elections, agricultural calendar, and administrative delays (authorities' approval, customs clearance, recruitment). In many contexts, recruiting for a key post takes 8 to 12 weeks and importing goods 3 to 6 months; a plan that ignores this is wrong from day one.
The first quarter of a project is almost always late. Planning expenditure in a linear way (one twelfth per month) guarantees a large variance by the third month.
2The critical path and float
The critical path is the longest sequence of dependent tasks; its duration is the project's minimum duration. Any task on the critical path that is delayed delays the whole project. The other tasks have float: they can slip without consequence, within the limit of that float.
Example. A: assessment (3 weeks). B: tender for the payment provider (6 weeks, after A). C: household registration (4 weeks, after A). D: verification of lists (2 weeks, after C). E: first payment (1 week, after B and D).
- Path A-B-E: 3 + 6 + 1 = 10 weeks.
- Path A-C-D-E: 3 + 4 + 2 + 1 = 10 weeks.
Both paths last 10 weeks: both are critical and no task has any float. A one-week delay on registration or on the tender pushes back the first payment. If the tender took 4 weeks, path A-B-E would take 8 weeks and task B would have 2 weeks of float.
To shorten a project, act only on the critical path: speeding up a task that has float changes nothing. Two techniques: do in parallel what was in sequence (start registration during the end of the assessment, with a risk of rework) and add resources to a critical task (two registration teams instead of one).
3The programme budget built on unit costs
A solid budget is built from activities, with verifiable unit costs: quantity × unit cost × duration or frequency. Each line has a justification (quotation, market price, salary scale, history). Donors mostly reject budgets where amounts are round, have no basis of calculation, or have no link with the logframe.
The budget usually distinguishes: direct activity costs (transfers, inputs, training), staff (with the share of time charged to the project), office running costs shared between projects according to a documented allocation key, monitoring and evaluation, and indirect costs (percentage set by the donor, often 7 to 10%).
Shared costs. An office costs 20,000 USD per month and serves three projects. The most defensible key is often staff time or budget share: if the project accounts for 40% of the office's direct expenditure, it takes 8,000 USD per month. The key must be written down, applied consistently and verifiable by an auditor.
A budget is not a ceiling to be reached: it is a forecast. Spending at the end of the project to "use up" the budget is a management fault that shows up in audits.
4Cost per person and cost per result
Two cost indicators inform decisions, provided they are well defined. The cost per person reached divides the total cost by the number of people assisted. It is simple but misleading: it favours programmes that give little to many people and says nothing about the effect.
The cost per result divides the cost by the effect obtained: cost per child cured of severe acute malnutrition, cost per household moving from insufficient to acceptable consumption, cost per water point still functional after one year. It allows approaches to be compared.
Example. Project A: 600,000 USD, 4,000 children admitted, cure rate 70%: cost per child cured = 600,000 / 2,800 = 214 USD. Project B: 450,000 USD, 3,500 children admitted, cure rate 55%: 450,000 / 1,925 = 234 USD. Project B seems cheaper per child admitted (129 against 150 USD), but it is more expensive per child cured.
The share of costs that directly reaches people (transfer ratio, or cost-transfer ratio for cash) measures delivery efficiency: for a cash programme, amount transferred / total cost. A ratio of 0.80 means that 80 cents of every dollar reach households. It is compared between similar programmes, never between very different modalities or contexts.
5Monitoring implementation: the burn rate
The burn rate compares cumulative actual expenditure with the expenditure planned in the cash-flow plan, not with a straight line. It is monitored every month, line by line, by the finance manager and the project manager together.
Example. 12-month budget: 900,000 USD. End of month 6: cumulative planned expenditure 420,000 USD (the plan allowed for a slow start), actual expenditure 290,000 USD. Implementation rate: 290,000 / 420,000 = 69%. At the current average rate (290,000 / 6 = 48,333 USD per month), 610,000 USD would remain to be spent in 6 months, i.e. 101,667 USD per month: more than double the current rate. Action is needed now.
The causes of underspending are almost always operational: delays in access, recruitment or procurement, postponed activities. The response follows this order: understand the causes line by line; speed up what can be sped up without loss of quality; propose a budget revision or a no-cost extension to the donor before the last months (most donors require a request at least 30 to 60 days before the end); never make unnecessary end-of-project purchases.
Conversely, an overspend on one line is offset within the flexibility provided in the contract (often 10 to 20% between lines or headings without prior approval). Beyond that, the donor's written approval is mandatory, otherwise the expenditure risks being declared ineligible.
6Programme human resources and organisation
The staffing plan follows from the work plan: how many enumerators are needed to register 3,000 households in 4 weeks? If one enumerator conducts 12 interviews per day over 20 working days per month, a team of 13 enumerators conducts 3,120 interviews in 4 weeks. The calculation avoids both teams that are too small (delays) and too large (costs, quality).
The programme organisation chart clarifies responsibility for each result and the segregation of duties: the person who selects beneficiaries must not be the one who approves payments or the one who handles complaints. The RACI matrix (responsible, accountable, consulted, informed) for each key process (registration, payment, monitoring, complaints) makes these separations visible and verifiable.
Finally, the programme manager organises a stable management rhythm: weekly team meeting on the work plan; monthly review of indicators, budget and risks; quarterly review with country management, which can decide on reallocations. A programme without a management rhythm discovers its problems in the final report.
Exercise: critical path and burn rate
Situation. Tasks: A, assessment (2 weeks); B, team recruitment (5 weeks, after A); C, purchase of kits (8 weeks, after A); D, team training (1 week, after B); E, distribution (2 weeks, after C and D). Total budget: 600,000 USD over 10 months. At the end of month 5, cumulative planned expenditure: 260,000 USD; actual expenditure: 182,000 USD.
Task. 1) Calculate the minimum duration and the critical path. 2) What is the float on recruitment? 3) Calculate the implementation rate and the monthly rate needed to spend the remaining budget.
Answer. A-C-E: 2 + 8 + 2 = 12 weeks. A-B-D-E: 2 + 5 + 1 + 2 = 10 weeks. Critical path: A-C-E, 12 weeks; recruitment has 2 weeks of float. To bring the distribution forward, act on the purchase of kits (launch the tender during the assessment, or use a framework agreement). Implementation: 182,000 / 260,000 = 70%. Remaining: 418,000 USD in 5 months, i.e. 83,600 USD per month against an average of 36,400 so far. The late lines must be identified and a revision or no-cost extension discussed with the donor now.
Key points
- Only the critical path determines the project's duration; speeding up a task that has float is useless.
- A budget is built by activity: quantity × unit cost × duration, with a justification for each line.
- Cost per result compares approaches better than cost per person reached.
- The burn rate is compared with the cash-flow plan, not a straight line, and is monitored every month.
- Budget revision or no-cost extension: request it early, never resort to end-of-project purchases.
💼 Monitoring, evaluation and data jobs
Put this course into practice: the latest jobs in this field.
- Monitoring & Evaluation Officer, Samriddhi projectLEPRA Society · India
- National Consultant -to support UN Women Ethiopia Country Office end line evaluation of the Project “Addressing the Effects of Conflict Related Sexual Violence in Ethiopia”ONU Femmes / UN Women · Ethiopia
- Temporary Research Assistants/Data collectors to collect data for the Value and Preference Study - UgandaPATH · Uganda
- Research & Insights Director – Jobtech AllianceMercy Corps · Kenya
- Research Analyst ConsultantPAM / WFP · Italy
Further reading: course references
- CHS Alliance, Groupe URD and the Sphere Project (2024). Core Humanitarian Standard on Quality and Accountability (CHS). www.corehumanitarianstandard.org
- Sphere (2018). The Sphere Handbook: Humanitarian Charter and Minimum Standards in Humanitarian Response. spherestandards.org
- OECD DAC (2019). Better Criteria for Better Evaluation: revised evaluation criteria. www.oecd.org
- ALNAP (M. Buchanan-Smith, J. Cosgrave and A. Warner) (2016). Evaluation of Humanitarian Action Guide. www.alnap.org
- United Nations Evaluation Group (UNEG) (2016). Norms and Standards for Evaluation. www.unevaluation.org
- IPC Global Partners (2021). Integrated Food Security Phase Classification (IPC) Technical Manual, Version 3.1. www.ipcinfo.org
- JIAF partners (2023). Joint Intersectoral Analysis Framework (JIAF 2.0). www.jiaf.info
- Washington Group on Disability Statistics (2022). The Washington Group Short Set on Functioning (WG-SS). www.washingtongroup-disability.com
- IASC (2019). IASC Guidelines on the Inclusion of Persons with Disabilities in Humanitarian Action. interagencystandingcommittee.org
- IASC (2019). Six Core Principles relating to Sexual Exploitation and Abuse. interagencystandingcommittee.org
- ICRC and Brussels Privacy Hub (2020). Handbook on Data Protection in Humanitarian Action, 2nd edition. www.icrc.org
- CALP Network (2023). The State of the World's Cash. www.calpnetwork.org
- P. Gertler, S. Martinez, P. Premand, L. Rawlings and C. Vermeersch (World Bank) (2016). Impact Evaluation in Practice, 2nd edition. www.worldbank.org
- J. Mayne (ILAC) (2008). Contribution analysis: an approach to exploring cause and effect. www.betterevaluation.org
Weekly quiz
5 demanding questions to check your learning. Answer them all to complete the week.