- Define a project, a programme and a portfolio, and distinguish a humanitarian project from ongoing operations.
- Describe the humanitarian project cycle and compare it with the cycles of PMBOK, PRINCE2, Agile and Project DPro (PMD Pro).
- Choose an approach (predictive, adaptive or hybrid) according to uncertainty, the donor and the context.
Keep the course at home: free PDF handout with exercises, key takeaways and quiz answers.
1Project, programme, portfolio
A project is a temporary endeavour undertaken to create a unique result: building 40 water points, delivering cash transfers to 3,000 households for six months, opening a mobile clinic. It has a start, an end, a budget, a team and defined objectives.
A programme groups several related projects to obtain benefits that no single project would deliver: for example a food security programme combining a cash project, an agricultural project and a nutrition project. A portfolio is all the projects and programmes of an organisation or country office, managed to achieve the strategy.
Operations, by contrast, are continuous: payroll, fleet management, warehouse upkeep. Many failures come from a confusion: a project that turns into an endless operation, with no clear budget or owner.
This programme is independent. PMI, PMP, CAPM and PMBOK are marks of the Project Management Institute; PRINCE2 is a mark of PeopleCert; Project DPro and PMD Pro belong to PM4NGOs. The Mini MBA prepares for and introduces these methods; it does not award their certifications.
2The humanitarian project cycle
Most humanitarian organisations follow a cycle of five or six stages, inspired by the European Commission's project cycle management:
- Identification: needs assessment, context and actor analysis, decision to intervene.
- Design: problem analysis, theory of change, logical framework, budget, proposal to the donor.
- Start-up and detailed planning: contract, recruitment, work plan, MEAL plan, procurement plan.
- Implementation and monitoring: activities, indicator tracking, risk and change management.
- Evaluation: mid-term or final, using the OECD DAC criteria.
- Closure: final report, financial closure, handover, lessons learned.
The cycle is not linear: monitoring feeds adjustments, and the lessons of one project feed the design of the next. In an acute emergency, stages overlap: we distribute before having a perfect logframe, and regularise afterwards.
3Landscape of methodologies
Project management methods do not compete; they answer different needs:
- PMBOK and PMP (Project Management Institute, United States): a body of knowledge, principles and performance domains, widely used worldwide; the PMP certification is the best known in the private sector and many agencies.
- PRINCE2 (PeopleCert, United Kingdom): a method structured by principles, practices and processes, with clear roles and control points; common in the UK, Europe and government-funded projects.
- Agile (Scrum, Kanban): adaptive approaches in short cycles, born in software and useful when the solution is not known in advance.
- Project DPro (formerly PMD Pro) (PM4NGOs): a guide and certification designed for the development and humanitarian sector, integrating the logframe, MEAL and donor requirements.
- Logical framework and results-based management (RBM): the design and accountability tools required by most donors (European Union, UN agencies, bilateral cooperation).
An effective humanitarian project manager borrows from each: the budget and contract rigour of predictive methods, PRINCE2's continued justification, Agile's short cycles for what is uncertain, and the results language donors expect.
4Predictive, adaptive or hybrid?
The approach is chosen by asking two questions: is the solution known? and are requirements likely to change?
- Predictive (or "waterfall"): when the deliverable is well defined and stable. Example: building a school from approved plans.
- Adaptive (agile): when we learn as we go. Example: designing a feedback and complaints mechanism with the community, or a data collection application.
- Hybrid: the most frequent case in humanitarian work. The contract, budget and logframe are fixed with the donor (predictive), but implementation arrangements are adjusted in short cycles to the context (adaptive).
Adaptive management is now encouraged by several donors, provided decisions are documented: why we change, on what data, with what approval.
5Where AI helps in the project cycle, and where it must not decide
Generative AI (Claude, Gemini, Copilot, and the AI features built into project management tools) can help at every stage:
- Identification: summarising public needs assessments, structuring a context analysis from your documents.
- Design: proposing a problem tree, a first draft logframe, critiquing the coherence of a proposal.
- Planning: breaking down the work, proposing a schedule, spotting forgotten dependencies.
- Monitoring: preparing dashboards, summarising minutes, analysing anonymised qualitative feedback.
- Reporting and closure: first drafts of reports, synthesis of lessons learned.
Three rules apply throughout the programme: never enter personal data about beneficiaries into a tool not approved by your organisation; check every figure produced by AI; keep the decision human for anything affecting people (targeting, selection, security, recruitment).
AI prepares, the project manager checks and decides. You remain responsible for everything you sign and send to the donor.
6The role of the humanitarian project manager
The project manager is responsible for delivering the agreed results within scope, schedule, budget and quality, while protecting people. In humanitarian work, add:
- accountability to affected populations (Core Humanitarian Standard, CHS);
- compliance with donor rules (eligibility of expenditure, procurement, visibility, reporting);
- the security of staff and partners;
- coordination with clusters, authorities and other actors.
PMI also describes expected skills along three axes: ways of working (project management techniques), power skills (leadership, negotiation, communication) and business acumen (strategy, environment, value). The new exams give growing weight to the third axis.
Exercise: choosing the approach for three projects
Situation. The country office of the fictitious NGO Amana must launch three projects: A) rehabilitate 12 boreholes from validated technical plans, budget USD 360,000 over 10 months; B) design with three communities a feedback and complaints mechanism adapted to women and older people, budget USD 45,000; C) a 6-month emergency cash programme whose transfer value depends on changes in market prices.
Task. 1) Which approach for each project? 2) For A, what is the average monthly budget? 3) Which task can be given to AI in each, and which must it be denied?
Answer. 1) A: predictive (known, stable deliverable). B: adaptive (learning with communities in short cycles). C: hybrid (fixed contractual frame, transfer value revised according to market monitoring). 2) 360,000 ÷ 10 = USD 36,000 per month on average (actual spending will follow the works schedule). 3) A: AI can propose the work breakdown and the schedule; it does not validate the engineers' technical choices. B: AI can synthesise anonymised feedback; it does not choose channels without consultation. C: AI can help analyse public price series; it does not select beneficiary households.
Key points
- A project is temporary and unique; a programme groups related projects; a portfolio serves the strategy.
- The humanitarian project cycle runs from identification to closure, with continuous monitoring and lessons learned.
- PMBOK/PMP, PRINCE2, Agile, Project DPro and the logframe are complementary.
- The hybrid approach is the most common: predictive contractual frame, adaptive implementation.
- AI prepares, people check and decide; no personal beneficiary data in a non-approved tool.
Ask the other participants: they are taking the same course as you.
💼 Programme management jobs
Put this course into practice: the latest jobs in this field.
- Chief Investment Officer (CIO) – TUFIDCNational Institute of Urban Management (NIUM) · India
- UN Women National Consultant - Technical Coordinator – Karachi, Sindh, PakistanONU Femmes / UN Women · Pakistan
- Program OfficerNavshristi Foundation · India
- Sign Language InterpreterThe American India Foundation Trust (AIFT) · India
- Тренер/ка-ментор/ка з розвитку спроможності Рад ветеранівIREX · Ukraine
Further reading: course references
- Project Management Institute (PMI) (2025). A Guide to the Project Management Body of Knowledge (PMBOK Guide), 8th edition. www.pmi.org
- Project Management Institute (PMI) (2026). PMP Examination Content Outline. www.pmi.org/certifications/project-management-pmp
- PeopleCert (AXELOS) (2023). Managing Successful Projects with PRINCE2, 7th edition. www.peoplecert.org
- Ken Schwaber and Jeff Sutherland (2020). The Scrum Guide. scrumguides.org
- Group of 17 signatories (2001). Manifesto for Agile Software Development. agilemanifesto.org
- PM4NGOs (2020). Project DPro: project management guide for development professionals (PMD Pro 2nd edition). pm4ngos.org
- PM4NGOs (2019). MEAL DPro: guide to monitoring, evaluation, accountability and learning. pm4ngos.org
- European Commission (2004). Project Cycle Management Guidelines. international-partnerships.ec.europa.eu
- United Nations Sustainable Development Group (UNSDG) (2011). Results-Based Management Handbook. unsdg.un.org
- CHS Alliance, Groupe URD and Sphere (2024). Core Humanitarian Standard on Quality and Accountability. www.corehumanitarianstandard.org
- Sphere Association (2018). The Sphere Handbook. spherestandards.org
- Inter-Agency Standing Committee (IASC) (2023). Operational Guidance on Data Responsibility in Humanitarian Action. interagencystandingcommittee.org
- ICRC and Brussels Privacy Hub (2020). Handbook on Data Protection in Humanitarian Action (2nd edition). www.icrc.org
- National Institute of Standards and Technology (NIST) (2023). AI Risk Management Framework (AI RMF 1.0). www.nist.gov
- United Nations (Chief Executives Board) (2022). Principles for the Ethical Use of Artificial Intelligence in the United Nations System. unsceb.org
Weekly quiz
5 demanding questions to check your learning. Answer them all to complete the week.