Week 3 of 12 · 12 hours · Month 1

PRINCE2: principles, practices, processes and roles applied to humanitarian work

Objectives of the week
  • Explain the five integrated elements of PRINCE2 7: principles, people, practices, processes and project context.
  • Use continued business justification, management by stages and management by exception in a donor-funded project.
  • Tailor PRINCE2 to an NGO (roles, documents, tolerances) and position the Foundation and Practitioner certifications.

Keep the course at home: free PDF handout with exercises, key takeaways and quiz answers.

Download this lesson as PDF Complete manual (PDF)

1Origin and logic of PRINCE2

PRINCE2 (PRojects IN Controlled Environments) is a method born in the UK public sector, now owned by PeopleCert (which acquired AXELOS). The 7th edition dates from 2023.

Where the PMBOK describes what you need to know, PRINCE2 describes how to organise and control a project: who decides what, when, on the basis of which documents. Public donors appreciate it because it makes governance readable.

PRINCE2 7 rests on five integrated elements: principles, people (new in the 7th edition: leadership, culture, change management), practices, processes and the project context, which requires the method to be tailored.

2The 7 principles

  1. Ensure continued business justification: the project must remain justified (benefits, costs, risks) from start to finish. If conflict makes the area inaccessible for a long time, the justification is reviewed instead of continuing out of inertia.
  2. Learn from experience: lessons are sought at the start, recorded along the way and passed on at closure.
  3. Define roles, responsibilities and relationships: who represents the interests of the organisation, the users and the suppliers.
  4. Manage by stages: the project is divided into management stages, with a formal decision at the end of each.
  5. Manage by exception: tolerances are set (time, cost, scope, quality, benefits, risk); as long as you stay within them, the lower level decides; beyond them, it escalates.
  6. Focus on products: deliverables and their quality criteria are defined precisely before activities are planned.
  7. Tailor to suit the project: the method adjusts to size, risk and context; a small NGO does not produce 30 documents.

3The 7 practices and the 7 processes

The practices (called "themes" before 2023) are aspects managed continuously: business case, organizing, plans, quality, risk, issues (which includes change management) and progress.

The processes describe the flow:

  • Starting up a project: check that the project is viable and worth launching;
  • Directing a project: project board decisions throughout;
  • Initiating a project: project plan, detailed business case, strategies;
  • Controlling a stage: the project manager's day-to-day work;
  • Managing product delivery: the team managers' work;
  • Managing a stage boundary: review and plan of the next stage;
  • Closing a project: acceptance, evaluation, lessons.

4The roles: the project board

The project board brings together three interests:

  • the executive, solely accountable, guardian of the justification: in an NGO, often the country director or programme director;
  • the senior user, who represents those who will use the results: in humanitarian work, make sure the voice of affected populations is carried, for example through community feedback and local partners;
  • the senior supplier, who represents those who produce: head of the technical department, construction company, implementing partner.

Below the board: the project manager, team managers, project assurance (independent oversight, for example the quality or MEAL team) and project support. One person may hold several roles in a small organisation, except executive and project manager, which must remain separate.

5Tailoring PRINCE2 to an NGO and using AI

A realistic tailoring for a project of EUR 300,000 to 2 million:

  • a project initiation document of 10 to 15 pages (business case, organisation, plan, tolerances, quality approach, risks, communication);
  • stages aligned with funding tranches or the donor's interim reports;
  • simple tolerances: for example ±10% on each main budget line and ±3 weeks on milestones;
  • a monthly one-page highlight report, and an exception report as soon as a tolerance is forecast to be exceeded.

AI helps produce these documents from your notes: "From these minutes, write a one-page PRINCE2 highlight report: progress, variances against tolerances, risks and issues, next actions. Do not invent any figure." It can also play the executive and ask the hard questions before the board. It replaces neither the project manager's analysis nor the board's decision.

6PRINCE2 certifications

Certifications are awarded by PeopleCert after an official exam:

  • PRINCE2 Foundation: knowledge of the method, multiple-choice exam, no prerequisites;
  • PRINCE2 Practitioner: application to a scenario, after the Foundation (or certain other recognised certifications);
  • PRINCE2 Agile: combines PRINCE2 governance with agile practices.

Formats, durations, pass marks and renewal rules change: check them on the official website before registering. This Mini MBA gives you the basics and case practice; the certification is obtained only through the official exam.

Exercise: tolerances and management by exception

Situation. Stage 2 of a food security project of the fictitious NGO Nahda: stage budget EUR 220,000, cost tolerance ±8%, time tolerance ±2 weeks. Halfway through the stage, the project manager forecasts a final stage cost of EUR 241,000, due to higher seed prices, and a 10-day delay.

Task. 1) What are the limits of the cost tolerance? 2) Does the forecast exceed the tolerances? 3) What must the project manager do?

Answer. 1) 8% × 220,000 = EUR 17,600; tolerance from 202,400 to 237,600 EUR. 2) Cost: yes, 241,000 > 237,600 (forecast overrun of EUR 3,400 beyond tolerance, i.e. +9.5% on the stage budget). Time: no, 10 days remain within ±2 weeks. 3) They must write an exception report to the board without delay: cause, impact, options (reduce quantities, change supplier, reallocate, ask the donor for a budget increase), recommendation. The board may request an exception plan to replace the stage plan.

Key points

  • PRINCE2 7 rests on 5 integrated elements: principles, people, practices, processes and context.
  • The 7 principles, including continued justification, management by stages and by exception, are mandatory.
  • The project board brings together the executive, the senior user and the senior supplier.
  • Tolerances determine who decides; a forecast overrun triggers an exception report.
  • PRINCE2 is tailored: an NGO keeps a few short documents, aligned with the donor's stages.
A question about this module?

Ask the other participants: they are taking the same course as you.

Ask my question See this module's discussions

💼 Programme management jobs

Put this course into practice: the latest jobs in this field.

See all 1171 Programme management jobs →

Prepare for the written test and interviewA model written test in this field, interview questions with sample answers and the STAR method.See the model test →
Further reading: course references
  1. Project Management Institute (PMI) (2025). A Guide to the Project Management Body of Knowledge (PMBOK Guide), 8th edition. www.pmi.org
  2. Project Management Institute (PMI) (2026). PMP Examination Content Outline. www.pmi.org/certifications/project-management-pmp
  3. PeopleCert (AXELOS) (2023). Managing Successful Projects with PRINCE2, 7th edition. www.peoplecert.org
  4. Ken Schwaber and Jeff Sutherland (2020). The Scrum Guide. scrumguides.org
  5. Group of 17 signatories (2001). Manifesto for Agile Software Development. agilemanifesto.org
  6. PM4NGOs (2020). Project DPro: project management guide for development professionals (PMD Pro 2nd edition). pm4ngos.org
  7. PM4NGOs (2019). MEAL DPro: guide to monitoring, evaluation, accountability and learning. pm4ngos.org
  8. European Commission (2004). Project Cycle Management Guidelines. international-partnerships.ec.europa.eu
  9. United Nations Sustainable Development Group (UNSDG) (2011). Results-Based Management Handbook. unsdg.un.org
  10. CHS Alliance, Groupe URD and Sphere (2024). Core Humanitarian Standard on Quality and Accountability. www.corehumanitarianstandard.org
  11. Sphere Association (2018). The Sphere Handbook. spherestandards.org
  12. Inter-Agency Standing Committee (IASC) (2023). Operational Guidance on Data Responsibility in Humanitarian Action. interagencystandingcommittee.org
  13. ICRC and Brussels Privacy Hub (2020). Handbook on Data Protection in Humanitarian Action (2nd edition). www.icrc.org
  14. National Institute of Standards and Technology (NIST) (2023). AI Risk Management Framework (AI RMF 1.0). www.nist.gov
  15. United Nations (Chief Executives Board) (2022). Principles for the Ethical Use of Artificial Intelligence in the United Nations System. unsceb.org

Weekly quiz

5 demanding questions to check your learning. Answer them all to complete the week.

1Who is solely accountable for a PRINCE2 project?
2Which element was added as an integrated element in PRINCE2 7?
3Management by exception relies on:
4Stage budget EUR 100,000, tolerance ±5%. A forecast of EUR 104,000:
5In PRINCE2 7, the "Issues" practice includes: