- Produce and read a budget monitoring report (budget versus actuals) line by line and by period.
- Build a realistic end-of-project forecast and draw decisions from it: accelerate, reallocate, revise or extend.
- Organise a useful monthly budget review between programmes and finance, with alert thresholds.
Keep the course at home: free PDF handout with exercises, key takeaways and quiz answers.
1The budget versus actuals report
The budget versus actuals report (BvA) is the basic tool for a project's financial management. For each budget line, it shows: the total budget, the budget planned to date (according to the spending plan, not a straight line), cumulative actual expenditure, commitments (orders placed but not yet paid), the variance and the burn rate.
Reading a BvA means asking three questions for each significant variance: why (activity delay, different prices, coding error, unbudgeted expense); is it temporary or lasting (a delay that will be caught up or a real saving); what decision (nothing, acceleration, reallocation, revision).
Example. "Hygiene kits" line: total budget 120,000 USD, budget to date 80,000, actual 30,000, commitments 45,000. The gross burn rate (30 / 80 = 38%) is worrying; taking orders placed into account, execution is (30 + 45) / 80 = 94%. Commitments completely change the reading: never analyse a BvA without them.
Usual analysis threshold: any variance of more than 10% and more than a set amount (for example 5,000 USD) on a line must be explained in writing every month.
2Price variances, quantity variances
A variance on an activity line can be broken down into two parts, which tells you whom to ask:
- Quantity variance = (actual quantity − planned quantity) × planned price. It is a programme matter: more or less was distributed than planned.
- Price variance = (actual price − planned price) × actual quantity. It is a procurement and market matter: the kits cost more or less.
Example. Planned: 2,000 kits at 45 USD = 90,000 USD. Actual: 1,800 kits at 52 USD = 93,600 USD. Total variance: +3,600 USD (overspend). Quantity variance: (1,800 − 2,000) × 45 = −9,000 USD (an apparent saving, because less was distributed). Price variance: (52 − 45) × 1,800 = +12,600 USD (extra cost). Check: −9,000 + 12,600 = +3,600. The real problem is not a 4% overspend: it is a price 15.6% higher than planned and 200 kits not distributed. If the remaining 200 kits are distributed at the new price, the line will be overspent by 14,000 USD.
The same logic applies to staff (headcount variance versus salary variance) and to cash transfers (variance in number of households versus variance in transfer value).
3The end-of-project forecast
The BvA tells you where you are; the forecast at completion tells you where you are heading. For each line: actual expenditure + commitments + estimate of what remains to be spent until the end, based on the updated workplan (not the initial budget). The forecast is compared with the total budget.
Example of a 12-month project, end of month 7.
| Line | Budget | Actual + committed | Estimated remaining spend | Forecast | Variance |
|---|---|---|---|---|---|
| Staff | 300,000 | 182,000 | 130,000 | 312,000 | +12,000 |
| Transfers | 500,000 | 210,000 | 220,000 | 430,000 | −70,000 |
| Vehicles and transport | 80,000 | 61,000 | 34,000 | 95,000 | +15,000 |
| Total | 880,000 | 453,000 | 384,000 | 837,000 | −43,000 |
Reading: the project will underspend by 43,000 USD overall, but two lines are overspent. Possible decisions: request a reallocation from transfers to staff and transport within the contract's flexibility; use the transfer balance to reach more households (which serves the objective); or propose a no-cost extension if delays prevent useful spending.
4Reallocations, revisions and flexibility
Each contract sets the budget flexibility: the percentage that may be transferred between lines or headings without prior approval (often 10 to 20% of a heading or of the total), protected lines (for example salaries or equipment, which always require approval), and the procedure for larger changes (amendment, budget revision).
Flexibility calculation. A contract with 15% flexibility between headings, calculated on the amount of the receiving heading. "Transport" heading: budget 80,000 USD. Up to 12,000 USD can be transferred to it without approval. In the previous example, 15,000 USD is missing: the 3,000 USD beyond the flexibility requires a formal request.
Good practice:
- Request revisions early (as soon as the forecast at completion shows a lasting variance), with a justification linked to activities and results, not just to figures.
- Never spend first and ask afterwards: an unauthorised overspend beyond the flexibility becomes an ineligible cost.
- Keep a written record of every donor approval, including by email, in the grant file.
- Update the reference budget in the accounting system after each approved revision, so that subsequent reports compare against the right budget.
5The monthly budget review
The monthly budget review (BvA meeting) brings together, for each project, the project manager, the finance manager and often the logistics manager. Duration: 30 to 60 minutes per project. Agenda:
- Significant variances and their explanations.
- Coding errors to be corrected (an expense of one project charged to another).
- Updated forecast at completion and decisions.
- Upcoming commitments (large orders, recruitments).
- Eligibility: unusual or risky expenditure to be checked before the report.
- Dates of the next financial reports and documents to be prepared.
The minutes record the decisions, who is responsible and the deadline. Recurring variances are escalated to country management, which consolidates the situation of all projects: total underspend, overspends, pre-financing, and the shared cost gap.
A budget review in which the project manager discovers the figures during the meeting is a wasted review. The report is sent three days in advance, and everyone comes with their explanations.
6Country portfolio indicators
At country or organisational level, management tracks a few portfolio indicators:
- Execution rate of each project against plan, and projects underspent by more than 20% less than six months before the end.
- Project end dates within six months, with their effect on funding for staff and shared costs (the "funding cliff").
- Shared cost coverage: amount recovered by projects against the office's actual costs.
- Pre-financing and receivables from donors by age.
- Costs at risk: expenditure whose eligibility is doubtful, provided for.
Funding cliff example. An office has 40 employees, 70% funded by two projects ending in June. If no new funding is signed by March, a staff reduction will have to be prepared in April, with the indemnities required by law and notice. Good management anticipates these dates six to nine months ahead.
Exercise: analysing a line and deciding
Situation. "Cash transfers" line of a 10-month project, end of month 6: planned 1,500 households × 6 months × 90 USD = 810,000 USD; actual 1,300 households × 6 months × 100 USD = 780,000 USD (the transfer value was raised by the cash working group). Total budget of the line: 1,350,000 USD. The contract provides 10% flexibility per heading.
Tasks. 1) Calculate the total variance, the quantity variance and the price variance. 2) Forecast the end of the line if 1,500 households receive 100 USD for the remaining 4 months. 3) What decision?
Answer. Total variance: 780,000 − 810,000 = −30,000 USD. Quantity: (1,300 − 1,500) × 6 × 90 = −108,000 USD. Price: (100 − 90) × 1,300 × 6 = +78,000 USD. Check: −108,000 + 78,000 = −30,000. Forecast: 780,000 + 1,500 × 4 × 100 = 1,380,000 USD, i.e. an overspend of 30,000 USD (2.2%), within the 10% flexibility if another line in the heading has a balance. Decision: document the increase in transfer value (cash working group decision), inform the donor, reallocate within the flexibility, and check why 200 households were not enrolled in the first six months.
Key points
- A budget versus actuals report without commitments gives a false picture of execution.
- Quantity variance = (Qa − Qp) × Pp; price variance = (Pa − Pp) × Qa.
- Forecast at completion = actual + committed + estimated remaining spend based on the updated workplan.
- Beyond the contract's flexibility, the donor's written approval is mandatory before spending.
- Anticipate project end dates six to nine months ahead to avoid the funding cliff.
💼 Finance, HR and admin jobs
Put this course into practice: the latest jobs in this field.
- AccountantIndian Grameen Services (IGS) · India
- Accounts ExecutiveCentre for Development Orientation and Training (CDOT) · India
- Consultant – ECCE Expert (Grant Project)ChildFund India · India
- Accountant - BhadrachalamWater, Sanitation and Hygiene Institute (WASH Institute) · India
- Chargé(e) de Projet, Empowered FuturesAmref Health Africa · Burkina Faso
Further reading: course references
- Office of Management and Budget (United States) (2024). Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (2 CFR 200). www.ecfr.gov/current/title-2/subtitle-A/chapter-II/part-200
- COSO (2013). Internal Control – Integrated Framework. www.coso.org
- United Nations Sustainable Development Group (UNSDG) (2014). Harmonized Approach to Cash Transfers (HACT) Framework. unsdg.un.org
- Inter-Agency Standing Committee (IASC) (2022). Guidance on the Provision of Overheads to Local and National Partners. interagencystandingcommittee.org
- Inter-Agency Standing Committee (IASC) (2021). The Grand Bargain 2.0 – Endorsed Framework and Annexes. interagencystandingcommittee.org/grand-bargain
- OCHA (2022). Country-Based Pooled Funds Global Guidelines. www.unocha.org/country-based-pooled-funds
- A. Goggins Gregory and D. Howard, Stanford Social Innovation Review (2009). The Nonprofit Starvation Cycle. ssir.org
- ACEVO and New Philanthropy Capital (2004). Full Cost Recovery: A Guide and Toolkit on Cost Allocation. www.thinknpc.org
- Charity Commission for England and Wales (2016). Charities' reserves: building resilience (CC19). www.gov.uk/government/publications/charities-and-reserves-cc19
- Charity Commission and OSCR (2019). Charities SORP (FRS 102). www.charitysorp.org
- IAASB (2016). International Standards on Auditing ISA 700 and ISA 705 (Forming an Opinion and Reporting on Financial Statements; Modifications to the Opinion in the Independent Auditor's Report). www.iaasb.org
- Association of Certified Fraud Examiners (ACFE) (2024). Occupational Fraud: A Report to the Nations. www.acfe.com/fraud-resources/report-to-the-nations-archive
- M. J. Nigrini (Wiley) (2012). Benford's Law: Applications for Forensic Accounting, Auditing, and Fraud Detection. www.wiley.com
- D. R. Cressey (1953). Other People's Money: A Study in the Social Psychology of Embezzlement. archive.org
Weekly quiz
5 demanding questions to check your learning. Answer them all to complete the week.