- Break the work down into work packages (WBS).
- Build a Gantt chart and identify the critical path.
- Assign roles (RACI) and keep a risk register.
1Breaking down the work (WBS)
The project breakdown structure (WBS, work breakdown structure) starts from the deliverables and breaks them down into ever smaller work packages, down to tasks that can be estimated (duration, cost, person responsible).
Example: “20 water points rehabilitated” → technical studies; procurement of materials; works; management committees trained; water quality control.
A useful rule: what is not in the WBS is not in the project.
2Gantt chart and critical path
The Gantt chart places each task on a timeline, with its dependencies (task B can only start once A is finished).
The critical path is the longest chain of dependent tasks: it gives the minimum duration of the project. A task on the critical path has no slack: any delay to it delays the end of the project. Other tasks have some slack (“float”).
In the field, international procurement, administrative authorisations and the rainy season are often on the critical path: plan them first.
3Who does what: the RACI matrix
For each task or decision, the RACI matrix shows who is:
- R (Responsible): does the work;
- A (Accountable): answers for it and approves it; only one person per task;
- C (Consulted): gives an opinion beforehand;
- I (Informed): is informed afterwards.
It avoids the two classic pitfalls: “everyone thought someone else was dealing with it” and “too many bosses for the same decision”.
4Risk register
A risk is an uncertain event which, if it occurs, affects the project. It is recorded with its probability and its impact (for example from 1 to 5); probability × impact gives its priority.
There are four possible responses: avoid (change the plan), reduce (lower the probability or impact), transfer (insurance, contract) or accept (with a contingency plan). Each risk has an owner and a review date.
| Risk | P | I | Score | Response |
|---|---|---|---|---|
| Road cut off in the rainy season | 4 | 4 | 16 | Reduce: preposition stock before June |
| Rise in cement prices | 3 | 3 | 9 | Reduce: fixed-price framework agreement |
The project plan also includes the procurement plan (what, when, which procedure), the budget, the monitoring and evaluation plan and the communication plan.
The delay in international procurement
Health project, remote area
You are planning the rehabilitation of 4 health centres in 9 months.
The medical equipment comes from abroad (lead time 14 weeks). The rainy season cuts off the road from month 5 to month 8.
Decision 1 of 3Where is the critical path probably located?
Decision 2 of 3Which response do you choose for the risk “road cut off”?
Decision 3 of 3In the RACI matrix, who is the “A” (accountable) for supplier selection?
Key takeaways
Identifying the critical path and addressing major risks early often makes the difference between a project delivered and a project extended.
Exercise: WBS, Gantt chart and risks
For your project from day 1, break one deliverable down into 6 to 10 tasks, estimate their duration and dependencies, draw a simple Gantt chart (on paper or in a spreadsheet) and identify the critical path. Add a RACI matrix for three tasks and a register of five scored risks.
Key points
- The WBS breaks deliverables down into tasks that can be estimated.
- The critical path sets the minimum duration: its tasks have no slack.
- RACI: only one “A” per task.
- Risk: probability × impact; responses: avoid, reduce, transfer, accept.
Further reading: course references
- PM4NGOs (2020). A Guide to the PMD Pro: Project Management for Development Professionals. www.pm4ngos.org
- European Commission (2004). Project Cycle Management Guidelines. international-partnerships.ec.europa.eu
- CHS Alliance, Groupe URD, Sphere (2024). Core Humanitarian Standard on Quality and Accountability (CHS). www.corehumanitarianstandard.org
- ALNAP (2022). The State of the Humanitarian System (report). www.alnap.org
Daily quiz
3 questions to check what you have learned. Answer them all to complete the day.