The consultant shall be responsible for the hydrogeological study and DPR for the full project area of around 50 villages in 5 Gram Panchayats.

List of Gram Panchayats- (Block – Binpur II, Jhargram)

  • Bhelaidiha
  • Shimulpal
  • Bhulaveda (Bhula Bheda)
  • Belpahari
  • Sandapara

The scope of work shall include, but not be limited to, the following.

A0. Inception

  • Review the project proposal, work plan, logical framework and the planned unit targets for water security works.
  • Hold a kick-off meeting with TF and agree the micro-watershed boundaries, priority villages and data-sharing arrangements with the baseline survey agency.
  • Prepare an Inception Report covering methodology, field plan, sampling of wells and test sites, team deployment, timelines and quality assurance.

Component A: Hydrogeological Characterisation and Micro-Watershed Delineation

A1. Desk review and secondary data

  • Collect and review existing data: Central Ground Water Board (CGWB) and State Water Investigation Directorate (SWID), West Bengal reports and aquifer maps, NAQUIM outputs where available, Geological Survey of India maps, block-level groundwater assessment category, rainfall records, any earlier watershed DPRs for the area, and the water-source inventory and water quality data from the project's baseline survey.
  • Obtain base layers: Survey of India toposheets (1:50,000), a digital elevation model (CartoDEM / SRTM, 30 m or finer), recent satellite imagery, land use/land cover, soil and geomorphology layers (e.g., Bhuvan / NRSC).

A2. Micro-watershed delineation and drainage mapping

  • Delineate watershed and micro-watershed boundaries from the DEM, validated against toposheets and field observation; reconcile with official micro-watershed codes where they exist.
  • Map the full drainage network and classify every drainage line by Strahler stream order, with slope, length and catchment area for each segment.
  • Divide each micro-watershed into ridge, mid-slope and valley zones to support ridge-to-valley treatment planning.
  • Produce thematic maps for each micro-watershed: drainage, slope, contour (at an interval suitable for structure design), geology, geomorphology, lineaments, soils and land use.

A3. Hydrogeological field investigation

  • Traverse the main drainage lines on foot and record lithology, rock outcrops, weathered-zone thickness, fractures, lineaments, dykes and stream-bed material at regular intervals.
  • Inventory existing open wells, bore wells and hand pumps (target: at least 200 wells across the 40 villages), recording location (GPS), depth, depth to water, construction, yield, use and seasonality.
  • Measure pre- and post-monsoon water levels in a network of key observation wells, and establish this network for long-term monitoring by the Foundation.
  • Conduct infiltration tests at representative sites across major soil and geology units (minimum 20 tests).
  • Carry out geophysical surveys (vertical electrical sounding or electrical resistivity tomography) at priority sites, particularly proposed injection-well and check-dam locations (minimum 40 soundings).
  • Collect and test groundwater samples at a NABL-accredited laboratory for basic potability and recharge-relevant parameters (pH, EC/TDS, hardness, chloride, nitrate, fluoride, iron, arsenic where relevant) from at least 40 sources, avoiding duplication with the baseline survey's testing.
  • Record existing water harvesting and recharge structures, their condition and performance.

A4. Aquifer characterisation and recharge profile

  • Define the aquifer type(s) (e.g., unconfined weathered zone, fractured hard rock, alluvial, confined), with geometry, thickness and water-bearing properties, illustrated with hydrogeological cross-sections.
  • Estimate the groundwater balance for each micro-watershed (rainfall, runoff, recharge, draft and stage of extraction) using an approach consistent with the GEC-2015 methodology.
  • Identify and map recharge zones, discharge zones and areas of over-extraction or water-quality concern.
  • Prepare a recharge-potential zonation map combining field data with weighted GIS layers.

A5. Site identification and prioritisation

  • Identify candidate sites for each structure type along drainage lines, matched to stream order, slope, geology and aquifer response, for example:
  • Ridge and upper reaches (1st–2nd order): trenches, gully plugs, loose boulder structures.
  • Mid reaches (2nd–3rd order): recharge trenches, percolation ponds, farm ponds.
  • Lower reaches (3rd–4th order): check dams, nala bunds, recharge shafts or injection wells where a permeable zone is confirmed.
  • Rank sites by expected recharge benefit, downstream beneficiaries, land availability and community preference.
  • Validate shortlisted sites with Gram Panchayats and user groups, and record land ownership and consent status.

Component B: Detailed Project Report (DPR) Preparation

B1. Intervention plan

  • Prepare a micro-watershed-wise treatment plan covering area treatment and drainage-line treatment from ridge to valley.
  • For each structure: unique ID, GPS location, survey number or land details, drainage order, type, purpose and justification from the hydrogeological findings.

B2. Engineering design

  • Carry out a topographic survey at every shortlisted structure site (levels, cross- and longitudinal sections).
  • Calculate catchment yield, design peak flood and storage capacity for each structure.
  • Prepare designs and drawings: plan, sections, dimensions, materials, foundation depth and spillway or overflow provision.
  • For injection or recharge wells: depth, casing, screen position, filter design and silt-trap arrangement, based on the geophysical and lithological data.
  • Follow applicable standards: CGWB Master Plan for Artificial Recharge to Groundwater, relevant Indian Standard codes, and the Common Guidelines for Watershed Development Projects / WDC-PMKSY 2.0 norms, or the State's own technical guidelines where these apply.

B3. Quantities and costs

  • Prepare bills of quantities and cost estimates for each structure using the current West Bengal Schedule of Rates (PWD / Irrigation & Waterways, as applicable) and MGNREGA rates, where applicable.
  • Summarise the budget by micro-watershed, structure type and implementation phase.
  • Identify components suitable for convergence with government schemes (e.g., MGNREGA, WDC-PMKSY, Jal Shakti Abhiyan, Atal Bhujal Yojana where applicable).

B4. Expected impact and monitoring

  • Estimate the additional storage and recharge volume, the area benefiting from irrigation and the households benefiting, for each structure and in total.
  • Propose a monitoring framework: observation wells, measurement frequency, indicators and a simple data format the Foundation's field staff can maintain.
  • Include an operation and maintenance plan, with roles for user groups and Gram Panchayats.

B5. Implementation and quality guidance

  • Set out a phased implementation schedule that sequences works ridge to valley and fits the working season.
  • Provide a quality supervision checklist for each structure type: critical dimensions, materials and stage-wise checks.
  • Note risks such as land, siltation and water quality, with mitigation measures.

B6. Stakeholder consultation and presentation

  • Present draft findings to the Foundation, Gram Panchayats and relevant government departments (e.g., Jhargram Zilla Parishad, Binpur-II Block Development Office, Water Resources Investigation & Development Department, Panchayat & Rural Development Department, Public Health Engineering Department).
  • Incorporate feedback and support the Foundation in sharing the final DPR for planning integration.

Responsibilities

All reports in English, in editable (Word/Excel) and PDF formats; all maps and spatial data as GIS files (shapefile/GeoPackage, WGS 84) with metadata. Payment is linked to TF's acceptance of each deliverable.

Deliverable

Key contents

Payment

1

Inception Report

Methodology, field plan, well and test-site sampling, team, work plan, QA

10%

2

Hydrogeological Characterisation and Micro-Watershed Report

  • Micro-watershed boundaries and drainage maps by stream order
  • Thematic maps
  • Well inventory
  • Post-monsoon water levels
  • Infiltration, geophysical and water quality results
  • Aquifer typology and cross-sections
  • Water balance
  • Recharge-potential zonation

25%

3

Site Prioritisation Package

Ranked, GPS-tagged site list per structure type with justification; Gram Panchayat validation and land consent status; Year-1 priority sites flagged

(with 4)

4

Draft DPR

Structure-wise designs, drawings, BoQs and SoR-based estimates; budget by micro-watershed and phase; convergence mapping; impact estimates; monitoring, O&M and quality supervision plans

30%

5

Validation Presentation

Presentation of findings and draft DPR to TF, Gram Panchayats and district/block officials

6

Final DPR

Final DPR incorporating feedback, with annexures, drawings, GIS database, raw field data, photographs and a summary presentation

25%

7

Pre-monsoon Addendum

Pre-monsoon water levels from the observation network, seasonal fluctuation analysis and any resulting site revisions

10%

Job posted by Tomorrow's Foundation, taken from its website. To apply, use the original posting. See the original posting ↗

Job information
Organization
Tomorrow's Foundation
Location
Jhargram District, India
Organization type
Local / national NGO
Contract
Consultancy
Posted
25 November 2026
Deadline
10 December 2026 15 days left

Duty station Jhargram District, India

Official travel advice (United Kingdom)
Advice against all travel to parts of the country
Life expectancy
72.2years (2024)
Physicians
0.72per 1,000 people (2020)
Basic drinking water access
95.7 % (2024)
Access to electricity
99.9 % (2024)
GDP per capita
$2,702 (2025)

Full country briefing → Jobs in India →

Public indicators: UK FCDO travel advice, World Bank. They do not replace your organization's security briefing. Sources : FCDO · World Bank.

Practise the interview for this job5 panel questions for this job, written or spoken. Score out of 10 and advice. Free with your account.Start the simulation → New programmeHumanitarian Mini MBAExactly three months to learn how to lead a humanitarian organisation: strategy, finance, compliance, fundraising, supply chain, HR, risk, negotiation and governance. Demanding, numerical and free.12 weeks · 144 hours3 exams · verifiable final certificateSelf-paced or cohortDiscover the Mini MBA → Improve my CV for TFSend your CV: Lumen rewrites it in NGO format for this position, with your cover letter. Free.Improve my CV →
New jobs by email

New jobs in India by email, every day or every week. Free, one-click unsubscribe.

Choose countries and sectors →

Our free services to apply for this job 100% free

Everything is free: no subscription, no credit card. Only the organisation's official vacancy notice is authoritative.

You will go to the organization's official site. Humanitaires Jobs never asks for money to apply.

⚠ Beware of scams: no genuine humanitarian organization charges application, visa or training fees.

Similar jobs

🎓 Scholarships not to miss

A master's or training to grow in humanitarian work? These scholarships close soon.

All scholarships on ScholarMap →