- Turn a programme plan into quantified needs (quantities, schedule) and a procurement plan.
- Calculate a safety stock, a reorder point and an order quantity, and monitor a pipeline.
- Organise joint planning between programmes, logistics and finance to avoid stock-outs and overstocks.
Keep the course at home: free PDF handout with exercises, key takeaways and quiz answers.
1From programme to quantified need
Planning starts with a simple question: what, how much, where, when. It requires close dialogue with programmes, who know the beneficiaries, and with finance, who know the budget.
Methods for estimating needs:
- By population: number of people × standard. Example: 12,000 people, 15 litres of water per person per day (Sphere minimum standard), i.e. 180 m³ per day.
- By past consumption: average stock issues over recent months, corrected for stock-outs (a stock-out lowers apparent consumption).
- By service: number of consultations × prescription rate. Example: 3,000 consultations per month, 30% receive an antimalarial: 900 treatments per month.
The procurement plan lists, for each item: specifications, quantity, date required, procurement method, estimated lead time, launch date, budget and budget line. The launch date is calculated backwards: date required − total lead time.
2Average consumption and forecasting
For an item with regular consumption, the average monthly consumption (AMC) over 3 to 6 months is used, corrected for:
- stock-out days: corrected AMC = observed consumption × days in the month / days with stock available;
- planned changes: new area, influx of displaced people, campaign, season.
Example. A health centre consumed 600, 640 and 450 sachets of ORS over three 30-day months; the third month had 10 stock-out days. Corrected consumption for the third month: 450 × 30 / 20 = 675. Corrected AMC = (600 + 640 + 675) / 3 ≈ 638. If a diarrhoea outbreak is expected with a 50% increase, the forecast for the season is 957 per month.
For seasonal items or items linked to a sudden-onset crisis, the forecast relies on scenarios (most likely, reasonable worst case) rather than on history.
3Safety stock and reorder point
Safety stock protects against two uncertainties: demand higher than expected and a delivery lead time longer than expected. A simple method, widely used in the sector:
Safety stock = AMC × safety margin (in months). The margin depends on variability: often 1 to 3 months in difficult contexts.
Reorder point = AMC × replenishment lead time (in months) + safety stock. When available stock reaches this level, the order is placed.
Maximum stock = reorder point + AMC × interval between orders.
Example. AMC 1,000 units, replenishment lead time 3 months, safety stock 2 months, review every 2 months. Safety stock = 2,000. Reorder point = 3,000 + 2,000 = 5,000. Maximum stock = 5,000 + 2,000 = 7,000. If available stock is 4,600 and 1,500 units are already on order, the quantity to order to return to the maximum is: 7,000 − 4,600 − 1,500 = 900 units.
Always count stock on order (the pipeline): forgetting it means ordering twice.
4The pipeline and pipeline breaks
A programme's pipeline (especially for food assistance or nutrition) tracks, month by month, needs, stocks, expected arrivals and funding. It makes it possible to anticipate a pipeline break several months in advance.
| Month | Opening stock | Arrivals | Needs | Closing stock |
|---|---|---|---|---|
| January | 900 t | 500 t | 700 t | 700 t |
| February | 700 t | 0 | 700 t | 0 |
| March | 0 | 400 t | 700 t | −300 t |
| April | 0 | 0 | 700 t | −700 t |
The break appears in March (300 t missing), then becomes total in April. With a procurement lead time of 4 months, the decision had to be taken in November. Options in January: borrow from another programme or from a national stock (with documented repayment), faster local or regional purchases, temporary reduction of the ration (a programme decision, communicated to beneficiaries), or prioritisation of the most vulnerable groups.
5Integrated planning
Stock-outs and overstocks rarely come from a calculation error. They come from a lack of coordination: the programme changes area without informing logistics, finance has not released the budget, the tender is waiting for a signature.
Good practices:
- Monthly planning meeting of programmes, logistics and finance: needs for the next three months, status of procurement, budget committed.
- Procurement plan validated at the start of each grant, aligned with the budget and the workplan.
- Shared indicators: procurement lead times, stock-out rate, months of stock available per item.
- Specification freeze: a change of specification after the tender is launched often costs weeks.
Months of stock available = available stock / AMC. A 9-month stock for an item with a 2-month lead time is an overstock: tied-up capital, risk of expiry and storage cost.
6Joint procurement, framework agreements and prepositioning
Three levers reduce lead times and costs when demand is recurrent:
- Framework agreement (long-term agreement): a supplier selected through competitive bidding commits to prices and lead times for 1 to 3 years; orders are placed as needs arise without re-tendering. Procurement lead time reduced by several weeks.
- Joint procurement between projects or between organisations: higher volumes, better prices, but heavier coordination.
- Prepositioning: contingency stocks close to at-risk areas before the cyclone or rainy season.
Calculating the benefit of a framework agreement. Without an agreement, 6 purchases per year, each with a 5-week tender and 2,000 USD in administrative cost. With an agreement, one 8-week tender every 2 years (5,000 USD) and an order lead time of one week. Annual administrative cost: 12,000 USD versus 2,500 USD; lead time per order: 5 weeks shorter. The safety stock required also falls, since the replenishment lead time is shorter.
Exercise: avoiding a stock-out of therapeutic food
Situation. Nutrition programme: 1,200 children admitted per month, each consumes on average 1.5 cartons of ready-to-use therapeutic food over their treatment. Available stock: 2,400 cartons; on order: 1,800 cartons expected in 2 months. Replenishment lead time: 3 months. Policy: 2-month safety stock, monthly review.
Tasks. 1) AMC. 2) Safety stock, reorder point and maximum stock. 3) Should you order, and how much? 4) When will stock run out without a new order?
Answer. 1) AMC = 1,200 × 1.5 = 1,800 cartons. 2) Safety stock = 3,600; reorder point = 1,800 × 3 + 3,600 = 9,000; maximum stock = 9,000 + 1,800 × 1 = 10,800. 3) Available stock + on order = 4,200, well below the reorder point: order 10,800 − 4,200 = 6,600 cartons immediately. 4) The stock of 2,400 covers 1.33 months; the 1,800 cartons arrive in month 2: at the end of month 1, 600 remain; during month 2, 1,200 cartons are missing before the arrival if it takes place at the end of the month. The stock-out is imminent: in parallel, request a loan from a partner or from the nutrition cluster's stock, and expedited delivery of the order in progress.
Key points
- Plan: what, how much, where, when; launch date = date required − total lead time.
- Correct consumption for stock-out days before calculating the AMC.
- Reorder point = AMC × lead time + safety stock; always deduct stock on order.
- The monthly pipeline reveals a break in time to act; the decision is taken one procurement lead time in advance.
- Framework agreements and prepositioning reduce lead times, costs and safety stocks.
💼 Logistics and procurement jobs
Put this course into practice: the latest jobs in this field.
- Logistics and Procurement Coordinator Iran South (Hormozgan Based)Norwegian Refugee Council (NRC) · Iran
- Spécialiste global Coordination & Intégration Logistique F/HHumanité & Inclusion (HI) · France
- Assistant (e) logistiqueACTED · Haiti
- Intern- AVIATION PROJECT MANAGEMENTDepartment of Operational Support · United States
- Senior Regional Technical Officer, Supply Chain KilimanjaroFHI 360 · Tanzania
Further reading: course references
- Global Logistics Cluster (2024). Logistics Operational Guide (LOG). dlca.logcluster.org
- Global Logistics Cluster (2024). Logistics Capacity Assessments (LCA). lca.logcluster.org
- Sphere (2018). The Sphere Handbook: Humanitarian Charter and Minimum Standards in Humanitarian Response. spherestandards.org
- International Chamber of Commerce (ICC) (2020). Incoterms® 2020. iccwbo.org/business-solutions/incoterms-rules
- P. Tatham and M. Christopher (Kogan Page) (2018). Humanitarian Logistics: Meeting the Challenge of Preparing for and Responding to Disasters. www.koganpage.com
- World Health Organization (2020). Good Distribution Practices for Pharmaceutical Products (Annex 7, Technical Report Series 1025). www.who.int
- World Health Organization and partners (2017). Interagency Emergency Health Kit (IEHK). www.who.int
- World Health Organization (2024). Performance, Quality and Safety (PQS) – catalogue of cold chain equipment. apps.who.int/immunization_standards/vaccine_quality/pqs_catalogue
- World Customs Organization (2006). International Convention on the Simplification and Harmonization of Customs Procedures (Revised Kyoto Convention), Specific Annex J5. www.wcoomd.org
- International Federation of Red Cross and Red Crescent Societies (2007). Guidelines for the Domestic Facilitation and Regulation of International Disaster Relief and Initial Recovery Assistance (IDRL Guidelines). disasterlaw.ifrc.org
- Inter-Agency Standing Committee (IASC) (2013). IASC Non-Binding Guidelines on the Use of Armed Escorts for Humanitarian Convoys. interagencystandingcommittee.org
- United Nations Security Council (2022). Resolution 2664 (humanitarian exemption to sanctions regimes). www.un.org/securitycouncil
- ICRC and International Federation (2021). Climate and Environment Charter for Humanitarian Organizations. www.climate-charter.org
- ICRC and Brussels Privacy Hub (2020). Handbook on Data Protection in Humanitarian Action (2nd edition). www.icrc.org
Weekly quiz
5 demanding questions to check your learning. Answer them all to complete the week.