- Build a consistent logical framework: vertical logic, horizontal logic, assumptions.
- Write SMART indicators with means of verification, baseline and target.
- Link the logical framework to the theory of change and to the monitoring and evaluation plan.
Keep the course at home: free PDF handout with exercises, key takeaways and quiz answers.
Your working day : 6 h
The course alone is not enough: this plan spreads the 6 hours of the day. Tick each step once done.
1The theory of change
The theory of change explains how and why the project's actions should lead to the intended change. It makes the intermediate steps and necessary conditions visible. Example: "If households have access to safe water within 500 m and adopt handwashing, then diarrhoea among children will decrease, because the main transmission routes will be cut, provided that the water points are maintained."
The theory of change is broader and more explanatory; the logical framework is its concise, measurable version, expected by most donors.
2Vertical logic
The logical framework is read from bottom to top:
- Activities: what the team does (drill, train, distribute).
- Outputs: what the project directly delivers and controls (15 functioning water points, 300 people trained).
- Outcomes (or specific objective): changes in behaviour or situation among beneficiaries (households use safe water).
- Impact (or goal): the long-term change to which the project contributes along with others (reduced child mortality).
The project manager is responsible for outputs. They influence outcomes but do not fully control them. Impact depends on many actors.
3Assumptions and the "if… and… then" logic
Assumptions are external conditions, outside the project's control, needed to move from one level to the next. The reading is: if the activities are carried out and the assumptions at this level hold, then the outputs will be achieved; and so on.
An assumption must not be a condition the project can guarantee itself (otherwise it is an activity to add). A very likely assumption does not need to be written; a very unlikely and decisive one is a "killer": the design must be reviewed.
4Horizontal logic: indicators and means of verification
Each level has its indicators, its means of verification (where and how the data will be collected) and its assumptions. An indicator states the baseline (at the start), the target and the deadline.
A good indicator is SMART: specific, measurable, achievable, relevant and time-bound. Weak example: "improved hygiene". Correct example: "% of targeted households reporting handwashing with soap at key times, from 15% (baseline, March) to 60% (end of project), KAP survey".
5From the logical framework to the monitoring and evaluation plan
The logical framework is not a document to file away after signature. It feeds the monitoring and evaluation plan: for each indicator, the definition, collection method, frequency, person responsible, tool and planned use of the data. It also sets the evaluation points (mid-term, final) and the questions they will ask.
PM4NGOs also publishes a free specialised guide on monitoring, evaluation, accountability and learning, MEAL DPro, which details these tools.
Exercise: repair a logical framework
Situation. A colleague proposes: impact "train 300 health workers"; outcome "15 water points built"; output "30% reduction in diarrhoea"; assumption "the team will carry out the activities on time".
Task. Find the four mistakes and rewrite correctly.
Answer. 1) "Train 300 workers" is an activity or output, not an impact. 2) "15 water points built" is an output, not an outcome. 3) "Reduction in diarrhoea" is an outcome or a contribution to impact, not an output. 4) Carrying out activities on time is under the project's control: it is not an assumption. Correct version: impact "contribute to reducing child mortality"; outcome "30% reduction in diarrhoea prevalence among under-5s"; outputs "15 functioning water points, 300 workers trained"; assumption "management committees maintain the water points".
Guided reading
Official, free documents. Answer the questions in writing: in an open-book exam, knowing where to look wins.
Project DPro Guide: logical framework and assumptions in the identification and definition phase
PM4NGOs, 2nd edition (free) · Open the document- Which levels does the guide use in the logical framework and what does it call them?
- How does the guide describe the role of assumptions?
- Which vocabulary in your language corresponds to each level (to understand the exam questions)?
MEAL DPro: guide to monitoring, evaluation, accountability and learning
PM4NGOs (free) · Open the document- What information does an indicator definition sheet contain?
- What difference does the guide make between monitoring and evaluation?
Deliverable of the day : Full logical framework for your common-thread project
Write the logical framework of your project: impact, one outcome, three outputs, two or three activities per output. For each level above activities: one or two SMART indicators with baseline and target, the means of verification and the assumptions. Add half a page with the matching theory of change ("if… and… then… because… provided that…").
Marking grid (out of 20)
| Correct vertical logic (no mixed levels) | 6 pts |
| SMART indicators with baseline, target and deadline | 6 pts |
| Realistic means of verification | 3 pts |
| External, plausible and well-placed assumptions | 3 pts |
| Theory of change consistent with the framework | 2 pts |
See the model answer points (after writing your deliverable)
What is expected. Outputs are delivered by the project ("15 functioning water points"); the outcome describes a change in people ("80% of households use an improved source"); impact is phrased as a contribution. Each indicator has a dated baseline. Assumptions are outside the project's control (prices, security, authorities' policies, maintenance by committees).
Key points
- Vertical logic: activities → outputs → outcomes → impact, read with "if… and… then".
- The project controls outputs, influences outcomes and contributes to impact.
- An assumption is external; if the project can guarantee it, it is an activity.
- SMART indicator with baseline, target, deadline and means of verification.
- The logical framework feeds the monitoring and evaluation plan (see also MEAL DPro).
Ask the other participants: they are taking the same course as you.
💼 Programme management jobs
Put this course into practice: the latest jobs in this field.
- Asistente de investigación sobre asuntos macroeconómicos, fiscales y de precios de la ArgentinaEconomic Commission for Latin America and the Caribbean · Argentina
- Facilitator for FPFSACDO · Afghanistan
- Consultant International CAPI, Coordonnateur des IT, en appui au processus du deuxième Recensement Général de la Population et de l’Habitat (RGPH2) de la RDCUNFPA · DR Congo
- Менеджер/ка з комунікацій / івент-менеджер/ка в ТатоХабГО ХОЦ Успішна жінка · Ukraine
- Regional Strategy & Business Development Advisor, WCA2Clinton Health Access Initiative (CHAI) · Burkina Faso
Further reading: course references
- PM4NGOs (2020). Project DPro Guide (PMD Pro, 2nd edition): project management for development professionals. pm4ngos.org/methodologies-guides/project-dpro
- PM4NGOs (2026). Exams & Certificates: format, rules and fees of the Project DPro exam. pm4ngos.org/candidates-and-learners/exams-certificates
- PM4NGOs (2024). Practice / Sample Exam: free Project DPro Foundation practice exam. pm4ngos.org/candidates-and-learners/practice-sample-exam/project-dpro-pmd-pro-foundation
- PM4NGOs (2019). MEAL DPro: monitoring, evaluation, accountability and learning guide. pm4ngos.org/methodologies-guides/meal-dpro
- CHS Alliance, Groupe URD, Sphere (2024). Core Humanitarian Standard on Quality and Accountability (CHS). www.corehumanitarianstandard.org
Daily quiz
8 questions to check what you have learned. Answer them all to complete the day.