Day 6 of 8 · 6 hours · Mock exam 2

Phase 3 (continued): resources, budget, procurement, risks and related plans

Learning objectives for today
  • Build a budget from the WBS and identify the donor rules to follow.
  • Plan human resources, logistics and procurement.
  • Analyse and respond to risks; prepare the communication, monitoring and sustainability plans.

Keep the course at home: free PDF handout with exercises, key takeaways and quiz answers.

Download this lesson as PDF Complete manual (PDF)

Your working day : 6 h

The course alone is not enough: this plan spreads the 6 hours of the day. Tick each step once done.

1Resources and budget

The budget is built from the work packages: for each one, the resources needed (staff, materials, transport, services) multiplied by their unit costs. Support costs (office, security, management) are added according to donor rules, and possibly a contingency if allowed.

The budget is linked to the schedule: the planned spending curve is used for financial monitoring and cash requests. Donor rules (eligible costs, flexibility between lines, exchange rates, indirect costs) must be known before spending.

Resource levelling moves activities within their float so that the same person or vehicle is not used twice at the same time.

2Procurement and logistics

The procurement plan lists what to buy, when, with which procedure (according to the organisation's and donor's thresholds: direct purchase, request for quotations, tender) and who decides. It is linked to the schedule: an international tender can take several months, often on the critical path.

Logistics also plans storage, transport, asset management and distribution. The basic principles: transparency, competition, segregation of duties, traceability of decisions.

3Risk management

A risk is an uncertain event that, if it occurs, affects the objectives. The process: identify (workshops, checklists, past lessons), analyse (probability × impact), plan the response, monitor.

Responses to negative risks: avoid (change the plan to remove the risk), reduce (lower probability or impact), transfer (insurance, contract), accept (with or without a fallback plan). Each risk has an owner.

Do not confuse: a risk is future and uncertain; an issue has already happened and is managed in the issue log.

4Communication and stakeholders

The communication plan says who receives what information, in what form, how often and from whom: donor reports, coordination meetings, information to communities in their language, feedback to authorities. It includes accessible and safe complaints and feedback channels.

It flows from the stakeholder analysis: each person receives the information useful at their level of engagement.

5Monitoring and evaluation plan, and sustainability

The monitoring and evaluation plan details each indicator of the logical framework (definition, method, frequency, person responsible, tool), the schedule of data collection and evaluations, and how the data will feed decisions.

The sustainability plan prepares from the planning stage what will remain after the project: who will maintain, with what resources, which skills will be transferred, how authorities or communities will take over. Thinking about sustainability at the end is too late.

Together, these plans form the project implementation plan, approved by governance before moving to implementation.

Exercise: risk register

Situation. Water project in Koro. Risks identified: A) 25% inflation on cement; B) rainy season blocking access to sites from July to September; C) a management committee that does not maintain the pumps; D) attack on the main road.

Task. For each: probability and impact (low, medium, high) and a response (avoid, reduce, transfer, accept).

Possible answer. A) likely, medium impact: reduce (fixed-price contract, early bulk purchase). B) almost certain, high impact: avoid (schedule works outside the season); it is almost a scheduling constraint. C) medium, high impact on sustainability: reduce (training, user contributions, post-project follow-up). D) low to medium, high impact: reduce (security analysis, alternative routes) and accept the residual risk with a suspension plan.

Guided reading

Official, free documents. Answer the questions in writing: in an open-book exam, knowing where to look wins.

  1. Project DPro Guide, "Project planning" phase: resources, budget, procurement, risks, communication, sustainability
    PM4NGOs, 2nd edition (free) · Open the document

    • Which plans does the guide include in the implementation plan?
    • Which risk responses does the guide propose?
    • How does the guide link the budget to the WBS and the schedule?
  2. Project DPro Guide, "integrated" principle (section 3) and sustainability plan
    PM4NGOs, 2nd edition (free) · Open the document

    • Why must the plans be integrated with each other?
    • When and how does the guide recommend preparing sustainability?

Deliverable of the day : Budget, procurement plan and risk register of your common-thread project

For your common-thread project: 1) a summary budget built from 6 WBS packages (quantities × unit costs); 2) a 5-line procurement plan (item, procedure according to the threshold, duration, deadline); 3) a register of 8 risks (probability, impact, response, owner); 4) a half-page sustainability plan.

Marking grid (out of 20)

Budget linked to the WBS, verifiable calculation5 pts
Procurement plan consistent with the schedule and thresholds4 pts
Complete risk register, suitable responses, named owners7 pts
Concrete sustainability (who, what, with what resources)4 pts
See the model answer points (after writing your deliverable)

Expected points. Each budget line refers to a package; the longest procurement lead times are identified and placed on the schedule; no risk is phrased as an issue that already exists; each risk has an owner; sustainability names a local structure and a source of funding for maintenance.

Key points

  • Budget built from the work packages, linked to the schedule, compliant with donor rules.
  • The procurement plan follows thresholds and can be on the critical path.
  • Risks: identify, analyse, respond (avoid, reduce, transfer, accept), monitor; one owner per risk.
  • Risk = future and uncertain; issue = already happened.
  • Plans are integrated; sustainability is prepared from the planning stage.
A question about this module?

Ask the other participants: they are taking the same course as you.

Ask my question See this module's discussions

💼 Programme management jobs

Put this course into practice: the latest jobs in this field.

See all 1290 Programme management jobs →

Prepare for the written test and interviewA model written test in this field, interview questions with sample answers and the STAR method.See the model test →
Further reading: course references
  1. PM4NGOs (2020). Project DPro Guide (PMD Pro, 2nd edition): project management for development professionals. pm4ngos.org/methodologies-guides/project-dpro
  2. PM4NGOs (2026). Exams & Certificates: format, rules and fees of the Project DPro exam. pm4ngos.org/candidates-and-learners/exams-certificates
  3. PM4NGOs (2024). Practice / Sample Exam: free Project DPro Foundation practice exam. pm4ngos.org/candidates-and-learners/practice-sample-exam/project-dpro-pmd-pro-foundation
  4. PM4NGOs (2019). MEAL DPro: monitoring, evaluation, accountability and learning guide. pm4ngos.org/methodologies-guides/meal-dpro
  5. CHS Alliance, Groupe URD, Sphere (2024). Core Humanitarian Standard on Quality and Accountability (CHS). www.corehumanitarianstandard.org

Daily quiz

8 questions to check what you have learned. Answer them all to complete the day.

1Taking out insurance for the project's vehicles is a risk response of the type:
2The project schedules works outside the rainy season so as not to be blocked. This is a response of the type:
3The materials truck has already been stuck at the border for three days. It is no longer a risk but:
4How do you build a solid project budget?
5Moving an activity within its float so that the same technician is not scheduled in two places on the same day is called:
6When should the sustainability plan be prepared?
7What should the communication plan include?
8A risk has high probability and high impact on the objectives. What is the priority?