- Build a budget from the WBS and identify the donor rules to follow.
- Plan human resources, logistics and procurement.
- Analyse and respond to risks; prepare the communication, monitoring and sustainability plans.
Keep the course at home: free PDF handout with exercises, key takeaways and quiz answers.
Your working day : 6 h
The course alone is not enough: this plan spreads the 6 hours of the day. Tick each step once done.
1Resources and budget
The budget is built from the work packages: for each one, the resources needed (staff, materials, transport, services) multiplied by their unit costs. Support costs (office, security, management) are added according to donor rules, and possibly a contingency if allowed.
The budget is linked to the schedule: the planned spending curve is used for financial monitoring and cash requests. Donor rules (eligible costs, flexibility between lines, exchange rates, indirect costs) must be known before spending.
Resource levelling moves activities within their float so that the same person or vehicle is not used twice at the same time.
2Procurement and logistics
The procurement plan lists what to buy, when, with which procedure (according to the organisation's and donor's thresholds: direct purchase, request for quotations, tender) and who decides. It is linked to the schedule: an international tender can take several months, often on the critical path.
Logistics also plans storage, transport, asset management and distribution. The basic principles: transparency, competition, segregation of duties, traceability of decisions.
3Risk management
A risk is an uncertain event that, if it occurs, affects the objectives. The process: identify (workshops, checklists, past lessons), analyse (probability × impact), plan the response, monitor.
Responses to negative risks: avoid (change the plan to remove the risk), reduce (lower probability or impact), transfer (insurance, contract), accept (with or without a fallback plan). Each risk has an owner.
Do not confuse: a risk is future and uncertain; an issue has already happened and is managed in the issue log.
4Communication and stakeholders
The communication plan says who receives what information, in what form, how often and from whom: donor reports, coordination meetings, information to communities in their language, feedback to authorities. It includes accessible and safe complaints and feedback channels.
It flows from the stakeholder analysis: each person receives the information useful at their level of engagement.
5Monitoring and evaluation plan, and sustainability
The monitoring and evaluation plan details each indicator of the logical framework (definition, method, frequency, person responsible, tool), the schedule of data collection and evaluations, and how the data will feed decisions.
The sustainability plan prepares from the planning stage what will remain after the project: who will maintain, with what resources, which skills will be transferred, how authorities or communities will take over. Thinking about sustainability at the end is too late.
Together, these plans form the project implementation plan, approved by governance before moving to implementation.
Exercise: risk register
Situation. Water project in Koro. Risks identified: A) 25% inflation on cement; B) rainy season blocking access to sites from July to September; C) a management committee that does not maintain the pumps; D) attack on the main road.
Task. For each: probability and impact (low, medium, high) and a response (avoid, reduce, transfer, accept).
Possible answer. A) likely, medium impact: reduce (fixed-price contract, early bulk purchase). B) almost certain, high impact: avoid (schedule works outside the season); it is almost a scheduling constraint. C) medium, high impact on sustainability: reduce (training, user contributions, post-project follow-up). D) low to medium, high impact: reduce (security analysis, alternative routes) and accept the residual risk with a suspension plan.
Guided reading
Official, free documents. Answer the questions in writing: in an open-book exam, knowing where to look wins.
Project DPro Guide, "Project planning" phase: resources, budget, procurement, risks, communication, sustainability
PM4NGOs, 2nd edition (free) · Open the document- Which plans does the guide include in the implementation plan?
- Which risk responses does the guide propose?
- How does the guide link the budget to the WBS and the schedule?
Project DPro Guide, "integrated" principle (section 3) and sustainability plan
PM4NGOs, 2nd edition (free) · Open the document- Why must the plans be integrated with each other?
- When and how does the guide recommend preparing sustainability?
Deliverable of the day : Budget, procurement plan and risk register of your common-thread project
For your common-thread project: 1) a summary budget built from 6 WBS packages (quantities × unit costs); 2) a 5-line procurement plan (item, procedure according to the threshold, duration, deadline); 3) a register of 8 risks (probability, impact, response, owner); 4) a half-page sustainability plan.
Marking grid (out of 20)
| Budget linked to the WBS, verifiable calculation | 5 pts |
| Procurement plan consistent with the schedule and thresholds | 4 pts |
| Complete risk register, suitable responses, named owners | 7 pts |
| Concrete sustainability (who, what, with what resources) | 4 pts |
See the model answer points (after writing your deliverable)
Expected points. Each budget line refers to a package; the longest procurement lead times are identified and placed on the schedule; no risk is phrased as an issue that already exists; each risk has an owner; sustainability names a local structure and a source of funding for maintenance.
Key points
- Budget built from the work packages, linked to the schedule, compliant with donor rules.
- The procurement plan follows thresholds and can be on the critical path.
- Risks: identify, analyse, respond (avoid, reduce, transfer, accept), monitor; one owner per risk.
- Risk = future and uncertain; issue = already happened.
- Plans are integrated; sustainability is prepared from the planning stage.
Ask the other participants: they are taking the same course as you.
💼 Programme management jobs
Put this course into practice: the latest jobs in this field.
- Asistente de investigación sobre asuntos macroeconómicos, fiscales y de precios de la ArgentinaEconomic Commission for Latin America and the Caribbean · Argentina
- Facilitator for FPFSACDO · Afghanistan
- Consultant International CAPI, Coordonnateur des IT, en appui au processus du deuxième Recensement Général de la Population et de l’Habitat (RGPH2) de la RDCUNFPA · DR Congo
- Менеджер/ка з комунікацій / івент-менеджер/ка в ТатоХабГО ХОЦ Успішна жінка · Ukraine
- Regional Strategy & Business Development Advisor, WCA2Clinton Health Access Initiative (CHAI) · Burkina Faso
Further reading: course references
- PM4NGOs (2020). Project DPro Guide (PMD Pro, 2nd edition): project management for development professionals. pm4ngos.org/methodologies-guides/project-dpro
- PM4NGOs (2026). Exams & Certificates: format, rules and fees of the Project DPro exam. pm4ngos.org/candidates-and-learners/exams-certificates
- PM4NGOs (2024). Practice / Sample Exam: free Project DPro Foundation practice exam. pm4ngos.org/candidates-and-learners/practice-sample-exam/project-dpro-pmd-pro-foundation
- PM4NGOs (2019). MEAL DPro: monitoring, evaluation, accountability and learning guide. pm4ngos.org/methodologies-guides/meal-dpro
- CHS Alliance, Groupe URD, Sphere (2024). Core Humanitarian Standard on Quality and Accountability (CHS). www.corehumanitarianstandard.org
Daily quiz
8 questions to check what you have learned. Answer them all to complete the day.