- Break the scope down into a work breakdown structure (WBS) down to work packages.
- Sequence activities, estimate durations and build a Gantt chart.
- Calculate the critical path and the float of an activity.
Keep the course at home: free PDF handout with exercises, key takeaways and quiz answers.
Your working day : 6 h
The course alone is not enough: this plan spreads the 6 hours of the day. Tick each step once done.
1Why plan in detail
The proposal and the charter give the frame. The planning phase produces the detailed plans needed to carry out and control the work: scope, schedule, resources, budget, procurement, risks, communication, monitoring and evaluation, sustainability. These plans are integrated: changing one changes the others.
Planning is not predicting perfectly. In an unstable context, you plan the near term in detail and the rest more broadly (rolling-wave planning), and revise regularly.
2Scope and the work breakdown structure
The scope describes all the work needed, and only that. The work breakdown structure (WBS) breaks it down hierarchically: project → outputs → sub-deliverables → work packages. A work package is small enough to be estimated (duration, cost), assigned to someone and monitored.
The 100% rule: the sum of the elements at one level represents 100% of the work of the level above, no more, no less. What is not in the WBS is not in the project: it is the best defence against scope creep.
A WBS dictionary describes each package: content, deliverable, person responsible, acceptance criteria.
3Activities, dependencies and estimates
Each work package is broken down into activities, then their dependencies are set. The most common is "finish-to-start": activity B only starts when A ends (you do not pour the slab before digging). There are also start-to-start, finish-to-finish and, rarely, start-to-finish.
Durations are estimated by analogy with past projects, by expert judgement, or with the three-point method: (optimistic + 4 × most likely + pessimistic) / 6. Example: 4, 6 and 14 days give (4 + 24 + 14) / 6 = 7 days.
In our sector, include real calendar constraints: rainy season, holidays, import lead times, administrative authorisations, the agricultural calendar.
4The Gantt chart and milestones
The Gantt chart shows activities as bars on a time scale, with their dependencies. Everyone can read it and it is used for monitoring: actual progress is compared with the planned bar.
Milestones are zero-duration events that mark an important point: contract signed, end of drilling, mid-term evaluation, interim report to the donor. They are useful for governance and reporting.
5The critical path
The critical path is the longest sequence of dependent activities: it sets the minimum duration of the project. Any critical-path activity that is late delays the whole project. Other activities have float (time they can slip without moving the end date).
Example. A (5 d) then B (10 d) then D (4 d); in parallel, A then C (6 d) then D. Path A-B-D = 19 days; path A-C-D = 15 days. The critical path is A-B-D, project duration 19 days, and C has a float of 10 − 6 = 4 days.
To shorten a project, act on the critical path: add resources (crashing, at a cost) or run activities in parallel (fast tracking, at a risk). Shortening a non-critical activity changes nothing to the end date.
Exercise: calculate the critical path
Data. A: site survey, 6 days. B: purchase of materials, 15 days, after A. C: training of committees, 8 days, after A. D: construction, 20 days, after B. E: commissioning, 3 days, after C and D.
Task. 1) List the paths and their durations. 2) What is the critical path? 3) What is C's float? 4) The supplier announces a 5-day delay on B: effect on the project?
Answer. 1) A-B-D-E = 6 + 15 + 20 + 3 = 44 days; A-C-E = 6 + 8 + 3 = 17 days. 2) A-B-D-E, 44 days. 3) C must finish at the latest on day 41 (start of E); it finishes at the earliest on day 14; float = 27 days. 4) B is critical: the project moves to 49 days, unless D is crashed or another supplier is found.
Guided reading
Official, free documents. Answer the questions in writing: in an open-book exam, knowing where to look wins.
Project DPro Guide, "Project planning" phase: scope and schedule
PM4NGOs, 2nd edition (free) · Open the document- How does the guide link the WBS to the logical framework?
- Which steps does the guide propose to build the schedule?
- Which words does the guide use for WBS, milestone, critical path and float?
Deliverable of the day : WBS and schedule of your common-thread project
For your common-thread project: 1) a three-level WBS with at least 12 work packages; 2) a list of at least 10 activities with durations and dependencies; 3) a simple Gantt chart (spreadsheet or paper, a photo is fine) with 4 milestones; 4) the critical path and the float of two non-critical activities; 5) two realistic ways to save 2 weeks if the donor asks.
Marking grid (out of 20)
| WBS meets the 100% rule, linked to outputs | 5 pts |
| Realistic dependencies and durations (seasons, lead times, permits) | 5 pts |
| Correct critical path and floats | 6 pts |
| Time-saving options quantified and applied to the critical path | 4 pts |
See the model answer points (after writing your deliverable)
Common mistakes. WBS mixing deliverables and support services; activities without dependencies; critical path calculated as the sum of all activities; time savings proposed on a non-critical activity (no effect on the end date).
Key points
- The WBS breaks the whole scope down to work packages; 100% rule.
- Most common dependency: finish-to-start. Three-point estimate: (O + 4M + P) / 6.
- Gantt = bars over time; milestone = zero-duration event.
- The critical path is the longest path; it sets the project duration; its activities have zero float.
- To shorten the project, act on the critical path (crashing or fast tracking).
Ask the other participants: they are taking the same course as you.
💼 Programme management jobs
Put this course into practice: the latest jobs in this field.
- Asistente de investigación sobre asuntos macroeconómicos, fiscales y de precios de la ArgentinaEconomic Commission for Latin America and the Caribbean · Argentina
- Facilitator for FPFSACDO · Afghanistan
- Consultant International CAPI, Coordonnateur des IT, en appui au processus du deuxième Recensement Général de la Population et de l’Habitat (RGPH2) de la RDCUNFPA · DR Congo
- Менеджер/ка з комунікацій / івент-менеджер/ка в ТатоХабГО ХОЦ Успішна жінка · Ukraine
- Regional Strategy & Business Development Advisor, WCA2Clinton Health Access Initiative (CHAI) · Burkina Faso
Further reading: course references
- PM4NGOs (2020). Project DPro Guide (PMD Pro, 2nd edition): project management for development professionals. pm4ngos.org/methodologies-guides/project-dpro
- PM4NGOs (2026). Exams & Certificates: format, rules and fees of the Project DPro exam. pm4ngos.org/candidates-and-learners/exams-certificates
- PM4NGOs (2024). Practice / Sample Exam: free Project DPro Foundation practice exam. pm4ngos.org/candidates-and-learners/practice-sample-exam/project-dpro-pmd-pro-foundation
- PM4NGOs (2019). MEAL DPro: monitoring, evaluation, accountability and learning guide. pm4ngos.org/methodologies-guides/meal-dpro
- CHS Alliance, Groupe URD, Sphere (2024). Core Humanitarian Standard on Quality and Accountability (CHS). www.corehumanitarianstandard.org
Daily quiz
8 questions to check what you have learned. Answer them all to complete the day.