- Close a project: deliverables, contracts, finances, resources, handover, lessons.
- Explain the five Project DPro principles and tailor the method to the size of the project.
- Apply an exam strategy and analyse your mistakes in the mock exams.
Keep the course at home: free PDF handout with exercises, key takeaways and quiz answers.
Your working day : 6 h
The course alone is not enough: this plan spreads the 6 hours of the day. Tick each step once done.
1Project closure
Closure is often rushed, yet it protects the organisation and sustainability. It includes:
- verification and acceptance of deliverables by their recipients (authorities, communities, partners);
- handover of assets and responsibilities according to the sustainability plan and donor rules;
- closing contracts (suppliers, partners) and commitments;
- financial closure: expenses justified, payments settled, final financial report, audit if planned;
- human resources: end of contracts, work certificates, support to the team;
- final reports, evaluation if planned, and archiving of documents for the required period;
- lessons learned, shared to improve future projects.
A project can also be closed early (insecurity, end of funding, need disappeared): the same steps apply, in an orderly way.
2The five Project DPro principles
The guide presents five principles that should guide all project management:
- Well-governed: clear roles, responsibilities and decision levels, and a project justification checked throughout the cycle.
- Participatory: stakeholders, starting with the people concerned, are involved in decisions.
- Comprehensive: the project is managed in all its dimensions (scope, schedule, resources, risks, quality, sustainability), not just activities.
- Integrated: plans and processes are linked with each other and with the organisation's functions (finance, logistics, HR).
- Adaptive: the project learns and adjusts to the context, within a controlled decision framework.
In the exam, a situation often describes a failure: identify the principle concerned.
3Tailoring the method to the project
The method is tailored to the project's size, complexity, risk and context. A 3-month, USD 20,000 project does not need the same documents as a 5-year, 10-million programme. But no phase disappears: you simplify the tools, not the logic (justify, authorise, plan, control, close).
4Exam-day strategy
- Before: check your connection and browser, have the digital guide open with your index, and no AI open.
- During: read the last sentence of the question first (what is being asked?), identify the phase concerned, eliminate answers that contradict a principle (deciding alone, hiding a problem, ignoring communities).
- Time: about 50 questions by the end of the first hour; keep 15 minutes for flagged questions.
- No blanks: there is no negative marking, answer everything.
Our mock exams do not show you the correct answers, so you train as on exam day. After each mock exam, work on your weak points with each day's quizzes and explanations.
5After you pass
The official Project DPro Foundation certificate is issued by PM4NGOs after your exam is validated. Our mock exam certificate only shows that you passed our training: it does not replace the official certification and must not be presented as such.
Possible next steps: the Practitioner level offered by some PM4NGOs partners, the MEAL DPro guide for monitoring and evaluation, or our Project Management and AI Mini MBA to go further.
Exercise: which principle is at stake?
Situations. A) The project was designed at headquarters without any consultation of villages. B) The project manager alone changes the location of an output without telling anyone. C) The budget was made with no link to the procurement plan or schedule. D) Although a road has been closed for 4 months, the plan has never been revised. E) The project tracked activities and budget, but never quality or sustainability.
Task. Match each situation with the principle not respected.
Answer. A) Participatory. B) Well-governed. C) Integrated. D) Adaptive. E) Comprehensive.
Guided reading
Official, free documents. Answer the questions in writing: in an open-book exam, knowing where to look wins.
Project DPro Guide, "Project closure" phase and section 3 "Principles"
PM4NGOs, 2nd edition (free) · Open the document- Which closure activities does the guide list?
- How does the guide define each of the five principles?
- What does section 4 say about tailoring Project DPro to different projects?
Free official Project DPro Foundation practice exam
PM4NGOs (free, in English) · Open the document- Take the official practice exam and note your score.
- Which types of questions did you find difficult? Go back to the matching day of this course.
Deliverable of the day : Closure checklist and review of your common-thread project
Write a closure checklist (at least 15 points) for your common-thread project, organised into: deliverables and handover, contracts, finances, human resources, documents and archives, lessons learned. Add half a page of lessons: three things to repeat, three to change, each linked to a Project DPro principle.
Marking grid (out of 20)
| Complete checklist covering the six headings | 8 pts |
| Concrete handover and sustainability | 4 pts |
| Useful lessons, linked to the principles | 5 pts |
| Clarity and precision | 3 pts |
See the model answer points (after writing your deliverable)
Points often forgotten. Acceptance report signed by recipients; handover of assets according to donor rules; closing unused commitments; archiving period required by the contract; work certificates for the team; sharing lessons beyond the team.
Key points
- Closure: acceptance, handover, contracts, finances, HR, reports, archives, lessons; also for early termination.
- Five principles: well-governed, participatory, comprehensive, integrated, adaptive.
- Tools are tailored to the size of the project, never the logic of the phases.
- On exam day: read the question, locate the phase, eliminate what contradicts a principle, answer everything.
- Our mock exam certificate does not replace the official certification issued by PM4NGOs.
Ask the other participants: they are taking the same course as you.
💼 Programme management jobs
Put this course into practice: the latest jobs in this field.
- Asistente de investigación sobre asuntos macroeconómicos, fiscales y de precios de la ArgentinaEconomic Commission for Latin America and the Caribbean · Argentina
- Facilitator for FPFSACDO · Afghanistan
- Consultant International CAPI, Coordonnateur des IT, en appui au processus du deuxième Recensement Général de la Population et de l’Habitat (RGPH2) de la RDCUNFPA · DR Congo
- Менеджер/ка з комунікацій / івент-менеджер/ка в ТатоХабГО ХОЦ Успішна жінка · Ukraine
- Regional Strategy & Business Development Advisor, WCA2Clinton Health Access Initiative (CHAI) · Burkina Faso
Further reading: course references
- PM4NGOs (2020). Project DPro Guide (PMD Pro, 2nd edition): project management for development professionals. pm4ngos.org/methodologies-guides/project-dpro
- PM4NGOs (2026). Exams & Certificates: format, rules and fees of the Project DPro exam. pm4ngos.org/candidates-and-learners/exams-certificates
- PM4NGOs (2024). Practice / Sample Exam: free Project DPro Foundation practice exam. pm4ngos.org/candidates-and-learners/practice-sample-exam/project-dpro-pmd-pro-foundation
- PM4NGOs (2019). MEAL DPro: monitoring, evaluation, accountability and learning guide. pm4ngos.org/methodologies-guides/meal-dpro
- CHS Alliance, Groupe URD, Sphere (2024). Core Humanitarian Standard on Quality and Accountability (CHS). www.corehumanitarianstandard.org
Daily quiz
8 questions to check what you have learned. Answer them all to complete the day.