Day 4 of 8 · 6 hours · Mock exam 1

Phase 2: project set-up, governance and charter

Learning objectives for today
  • Describe what happens between the funding agreement and detailed planning.
  • Put the project's governance in place: roles, bodies, decision levels.
  • Write a project charter and organise the launch with stakeholders.

Keep the course at home: free PDF handout with exercises, key takeaways and quiz answers.

Download this lesson as PDF Complete manual (PDF)

Your working day : 6 h

The course alone is not enough: this plan spreads the 6 hours of the day. Tick each step once done.

1What the set-up phase is for

Funding has been granted. Should activities start right away? No. The set-up phase turns a proposal into an authorised, organised project. It checks that the commitments made in the proposal (sometimes written months earlier) are still valid, then puts in place what is needed to plan and deliver.

It includes in particular: review of the contract and donor requirements, updating the proposal if the context has changed, governance, the project charter, the team, the launch and stakeholder engagement.

2Project governance

Governance defines who decides what, at what level, and how information flows up. It usually relies on:

  • a sponsor in the organisation, responsible for the project's justification;
  • a steering committee that takes major decisions (major changes, decision gates);
  • the project manager, responsible for day-to-day management within their delegated authority;
  • representatives of partners, authorities and, as far as possible, communities.

Tolerances set the project manager's room for manoeuvre (for example a 10% variance on a budget line). Beyond that, they escalate the decision. A RACI matrix (responsible, accountable, consulted, informed) clarifies roles; there should be only one "accountable" per decision.

3The project charter

The charter is the document that formally authorises the project and gives the project manager authority to use resources. Short (2 to 4 pages), it covers: justification and objectives, scope and main deliverables, what is excluded, overall schedule and budget, main risks and assumptions, governance and roles, success criteria.

It is signed by the sponsor. For the exam, remember: the charter authorises and frames; it does not replace the detailed plans produced during planning.

4The team and partners

Set-up organises the team: profiles, recruitment, organisation chart, job descriptions, security. With implementing partners, capacities are checked, an agreement is signed specifying roles, budget, reporting and compliance rules, and support is planned if needed.

Passing donor requirements on to partners (procurement rules, eligibility of expenditure, visibility, protection from sexual exploitation and abuse) must be explicit: the project manager remains accountable to the donor.

5The launch and the decision gate

The launch workshop brings together the team, partners and key stakeholders: presentation of objectives, logical framework, governance, schedule, donor rules and complaints and feedback mechanisms. It is also the moment to tell communities what the project will and will not do.

The end-of-set-up decision gate checks that the project is authorised, governed and staffed, and that detailed planning can begin.

Exercise: tolerances and escalation

Situation. USD 180,000 project. Tolerances set by the steering committee: ± 10% per budget line and 3 weeks on the schedule. Three events: A) the "transport" line (USD 12,000) will be overspent by USD 1,500; B) the "materials" line (USD 60,000) will be overspent by USD 9,000; C) one borehole will be 2 weeks late with no effect on the end date.

Task. Who decides in each case?

Answer. A) 1,500 / 12,000 = 12.5%: beyond the 10% tolerance, escalate to the committee. B) 9,000 / 60,000 = 15%: beyond, escalate to the committee and check the donor's rules on transfers between lines. C) 2 weeks, within tolerance: the project manager handles it and reports it.

Guided reading

Official, free documents. Answer the questions in writing: in an open-book exam, knowing where to look wins.

  1. Project DPro Guide, "Project set-up" phase
    PM4NGOs, 2nd edition (free) · Open the document

    • Which activities does the guide place in project set-up?
    • How does the guide describe governance and the sponsor's role?
    • What does the project charter contain according to the guide?
  2. The "well-governed" principle in section 3 of the guide
    PM4NGOs, 2nd edition (free) · Open the document

    • What makes a project "well governed"?
    • Give an example from your experience where governance was unclear, and its consequences.

Deliverable of the day : Charter and governance of your common-thread project

Write your project charter (2 pages maximum): justification, objectives, scope included and excluded, deliverables, overall budget and schedule, 5 main risks, success criteria. Add a governance diagram (bodies, meeting frequency, quantified tolerances) and a RACI matrix for 5 recurring decisions.

Marking grid (out of 20)

Complete charter, explicit exclusions6 pts
Clear governance with quantified tolerances5 pts
Correct RACI (only one "accountable" per decision)5 pts
Communities and partners genuinely included4 pts
See the model answer points (after writing your deliverable)

Example. Excluded: "the project does not build a piped network; it does not cover health costs". Tolerances: 10% per line, 3 weeks per milestone, no change of output without the committee. RACI "choice of sites": responsible = project manager, accountable = steering committee, consulted = communities and authorities, informed = donor.

Key points

  • Set-up turns a funded proposal into an authorised, governed and organised project.
  • Governance: sponsor, steering committee, project manager, tolerances, RACI with only one "accountable".
  • The charter authorises the project and gives authority to the project manager; it does not replace detailed plans.
  • Donor requirements are explicitly passed on to partners.
  • The launch also tells communities what the project will and will not do.
A question about this module?

Ask the other participants: they are taking the same course as you.

Ask my question See this module's discussions

💼 Programme management jobs

Put this course into practice: the latest jobs in this field.

See all 1290 Programme management jobs →

Prepare for the written test and interviewA model written test in this field, interview questions with sample answers and the STAR method.See the model test →
Further reading: course references
  1. PM4NGOs (2020). Project DPro Guide (PMD Pro, 2nd edition): project management for development professionals. pm4ngos.org/methodologies-guides/project-dpro
  2. PM4NGOs (2026). Exams & Certificates: format, rules and fees of the Project DPro exam. pm4ngos.org/candidates-and-learners/exams-certificates
  3. PM4NGOs (2024). Practice / Sample Exam: free Project DPro Foundation practice exam. pm4ngos.org/candidates-and-learners/practice-sample-exam/project-dpro-pmd-pro-foundation
  4. PM4NGOs (2019). MEAL DPro: monitoring, evaluation, accountability and learning guide. pm4ngos.org/methodologies-guides/meal-dpro
  5. CHS Alliance, Groupe URD, Sphere (2024). Core Humanitarian Standard on Quality and Accountability (CHS). www.corehumanitarianstandard.org

Daily quiz

8 questions to check what you have learned. Answer them all to complete the day.

1Which document formally authorises the project and gives the project manager authority to use resources?
2A forecast 15% overspend on a line, when the tolerance is 10%, must be:
3In a RACI matrix, how many people should be "accountable" for the same decision?
4Funding has just been granted, eight months after the proposal. What is the priority during set-up?
5Who remains accountable to the donor for an implementing partner's compliance with the rules?
6What does a project charter normally contain?
7Which element shows that a project is "well governed"?
8Why inform communities during the launch?