- Lead implementation: coordinate the team, partners and suppliers.
- Monitor progress, compare it with the plan and decide on actions.
- Manage changes, issues and reporting according to governance rules.
Keep the course at home: free PDF handout with exercises, key takeaways and quiz answers.
Your working day : 6 h
The course alone is not enough: this plan spreads the 6 hours of the day. Tick each step once done.
1Doing the work
Implementation carries out the plan: mobilise the team and partners, launch procurement, carry out activities, deliver outputs. The project manager coordinates, motivates, removes blockages, protects the team and ensures quality and accountability.
Everyday tools: short regular meetings, monthly work plan, task tracking board, field visits, meetings with partners and community committees.
2Monitor and control
Monitoring collects and analyses information on progress (activities, outputs, spending, schedule, risks, indicators). Control compares reality with the baseline plan and decides on corrective actions (to get back on plan) or preventive ones (to avoid a future variance).
Example: at mid-term, 40% of the budget is spent while 60% of the planned work should be done, and only 35% actually is. The project is behind schedule (35% done instead of 60% planned) and costs more than planned for the work done (40% spent for 35% done). Analyse the causes before acting.
3Change control
A change in scope, schedule or budget is never decided alone and verbally. The change control process: 1) written request; 2) analysis of the impact on all constraints (scope, time, cost, quality, risks, beneficiaries); 3) decision at the competent level according to tolerances, and by the donor if the contract requires; 4) update of the plans; 5) informing stakeholders.
Scope creep is the gradual addition of unapproved work ("while you are here, also build…"). It consumes budget and time without a decision. The reflex: thank the person, record the request and put it through the process.
4Issues, decisions and lessons along the way
The issue log records each issue: description, date, impact, owner, action, deadline, status. The decision log keeps track of who decided what and why, useful for audit and adaptive management.
Lessons should not wait until the end: a short review after each important stage makes it possible to correct course during the project.
5Reporting and accountability
Reports serve decision-making, not only the donor: monthly internal report (progress, spending, risks, issues, decisions requested), narrative and financial reports to the donor, feedback to communities on what has been done and on the follow-up given to their complaints.
A good report is accurate, compares actual with planned, explains variances and proposes actions. It does not hide problems: transparency is an accountability requirement.
Exercise: change request
Situation. The village chief asks the project to add 2 water points near the school, on top of the 15 planned. Estimated cost: USD 14,000; extra time: 4 weeks; tolerances: 10% of the budget (USD 180,000) and 3 weeks.
Task. What do you tell the village chief, and what path does the request follow?
Answer. Thank them and explain that any change must be studied and decided, without promising anything. Write a change request and analyse the impact (14,000 / 180,000 = 7.8% of the budget, within tolerance; but 4 weeks, beyond the 3-week tolerance; a change of output, so outside delegated authority). The decision belongs to the steering committee, and probably to the donor since an output changes. Then update the plans and tell the community the answer.
Guided reading
Official, free documents. Answer the questions in writing: in an open-book exam, knowing where to look wins.
Project DPro Guide, "Project implementation" phase
PM4NGOs, 2nd edition (free) · Open the document- Which monitoring and control processes does the guide describe?
- How does the guide describe change control?
- Which logs and registers does the project manager keep during implementation?
Deliverable of the day : Monthly report and change request for your common-thread project
Imagine month 6 of your common-thread project. Write: 1) a one-page monthly report (planned and actual progress, planned and actual spending, 3 updated risks, 2 issues and their actions, decisions requested from the committee); 2) a complete change request for a realistic change (description, reason, quantified impacts, options, recommendation, decision level).
Marking grid (out of 20)
| Planned / actual comparison quantified and interpreted | 6 pts |
| Risks and issues clearly separated, actions and owners | 4 pts |
| Complete change request with impacts on all constraints | 6 pts |
| Correct decision level according to tolerances and the contract | 4 pts |
See the model answer points (after writing your deliverable)
Expected points. The report clearly says whether the project is ahead or behind, and whether it costs more or less than planned for the work done. The change request presents at least two options (including "change nothing") and states whether the donor must approve.
Key points
- Monitor = collect and analyse; control = compare with the plan and act (corrective or preventive).
- Compare work done with work planned and with actual spending before concluding.
- No change of scope, time or budget without a written process and a decision at the right level.
- Scope creep is fought by putting every request through change control.
- Issue log, decision log, honest reports and feedback to communities.
Ask the other participants: they are taking the same course as you.
💼 Programme management jobs
Put this course into practice: the latest jobs in this field.
- Asistente de investigación sobre asuntos macroeconómicos, fiscales y de precios de la ArgentinaEconomic Commission for Latin America and the Caribbean · Argentina
- Facilitator for FPFSACDO · Afghanistan
- Consultant International CAPI, Coordonnateur des IT, en appui au processus du deuxième Recensement Général de la Population et de l’Habitat (RGPH2) de la RDCUNFPA · DR Congo
- Менеджер/ка з комунікацій / івент-менеджер/ка в ТатоХабГО ХОЦ Успішна жінка · Ukraine
- Regional Strategy & Business Development Advisor, WCA2Clinton Health Access Initiative (CHAI) · Burkina Faso
Further reading: course references
- PM4NGOs (2020). Project DPro Guide (PMD Pro, 2nd edition): project management for development professionals. pm4ngos.org/methodologies-guides/project-dpro
- PM4NGOs (2026). Exams & Certificates: format, rules and fees of the Project DPro exam. pm4ngos.org/candidates-and-learners/exams-certificates
- PM4NGOs (2024). Practice / Sample Exam: free Project DPro Foundation practice exam. pm4ngos.org/candidates-and-learners/practice-sample-exam/project-dpro-pmd-pro-foundation
- PM4NGOs (2019). MEAL DPro: monitoring, evaluation, accountability and learning guide. pm4ngos.org/methodologies-guides/meal-dpro
- CHS Alliance, Groupe URD, Sphere (2024). Core Humanitarian Standard on Quality and Accountability (CHS). www.corehumanitarianstandard.org
Daily quiz
8 questions to check what you have learned. Answer them all to complete the day.